Tuesday, 11 May 2021

Wembley Park road changes update

 

A glimpse of the new Bridge Road- North End Road junction. At present it is a steep ramp but aggregate was being delivered this morning presumably to reduce the gradient. There are  reports that there will be weight restrictions when it opens. Brent Council has said it should be open to pedestrians by the end of the month.

The mural on Olympic Way is covered again apart from one section but correspondence is still taking place over whether planning permission for advertising is actually in place.

Behind the ramp on the right is 1 Olympic Way, former office accommodation being converted to flats.

The length of Olympic Way up to the infamous steps is nearing completion.

 

There is no word yet on when Engineers Way will be open again to traffic. 'Hostile Vehicle Mitigation Measures' have to be put in place.


1 comment:

  1. The Legal Notices in this week's "Brent & Kilburn Times" include one imposing a 7.5 tonne weight limit in North End Road.

    ReplyDelete