Showing posts with label FMConway. Wembley High Road. Show all posts
Showing posts with label FMConway. Wembley High Road. Show all posts

Wednesday, 20 October 2021

Brent Council attempts to clear up confusion over Wembley High Road improvement works that are due to start on Monday and last beyond April 2022. They promise disruption will be 'kept to a minimum.'

 


Work will start on Monday on improvements to Wembley High Road and is organised in four phases. The first 3 phases are expected to be completed in April 2022 but depending on delivery of materials:

Phase 1 From Ark Elvin Academy to Park Lane (both sides of the road)

Phase 2 From Park Lane to Wembley Central Square (both sides of the road)

Phase 3 From Wembley Central Square to Ealing Road (both sides of the road)

Phase 4 From Wembley Triangle to the Ark Elvin Academy (both sides of the road) and from Ealing Road to Napier Road (both sides of the road)

This is the document sent to local residents and businesses:


 

In an email update sent yesterday, Brent Council said:

 

We do understand there is some concern and confusion around these works so hopefully the following information can help clear up any confusion

 

The purpose of these works is to improve the look and feel of the Wembley High Road area to help encourage more shoppers into the locale and thereby help businesses. Please click on the following link to learn more -  Brent Council - Revitalising our high streets

 

As with any town centre improvement works, there will be some disruption however, we can confirm that steps will be taken to ensure any disruption is kept to a minimum and that your business can continue to operate in a ‘Business As Usual’ manner. FM Conway, the contractors conducting these works on our behalf will ensure that:

 

Loading bays

Although some loading bays may need to be suspended during the works in that specific location, the site team will ensure that you will still be able to receive deliveries so your business remains unaffected. Any loading bay closure will be kept to a minimum and be re-opened once the work in that specific location has been completed. FM Conway have a Business/Residents Liaison Officer employed on the scheme. She will keep you updated on the works and work with you regarding any specific delivery requirements. Her contact details are:

Cate Green Catherine.Green@fmconway.co.uk telephone number 07443 077444.

Should you have any further questions relating to this information or the scheme in general please do not hesitate to contact her.

 

Business As Usual

All customers will continue to access your business during the works. The site  teams will NOT block entrances to business premises during opening hours. Direct access into properties might not always be possible, however. This is to enable larger sections of sett laying/paving to be completed, without too much stone cutting, but more importantly, to provide a safe width of footpath for pedestrians. 

 

In addition, where premises have larger entrances, half the access may be worked on during working hours. For those businesses that have more than one entrance it may only be possible to retain one point of access or egress during opening hours.

 

Fencing will be erected to ensure any dust and debris from the works is kept to a minimum. We will attach boards onto the fencing so anyone passing through the area will know your business is still open during the works.

 

 

Businesses With Private Forecourts

We are aware that some businesses have a private forecourt. If you do have a Private Forecourt and you would like your forecourt upgraded in keeping with the wider works this can be done free of charge. There is a twelve month defect period during which time, any issues relating to the surface will be repaired by Brent Council, however after this period, any future maintenance will revert back to the landowner. This is standard practise and is currently the case for Wembley and other town centres across Brent and London. 

 

Will junctions be closed?

All junctions will remain open, however St Johns Road will be closed so materials and equipment needed for the works can be stored, however it will remain open for emergency vehicles to have access and for delivery vehicles that use this location to make deliveries to businesses in this location.

 

 

As mentioned previously, FM Conway have a Business/Residents Liaison Officer employed on this scheme. Please do not hesitate to contact Cate Green via email on Catherine.Green@fmconway.co.uk or by phone on 07443 077444 should you have any further questions relating to this information or the scheme in general.