Showing posts with label Willesden Green library Regeneration. Show all posts
Showing posts with label Willesden Green library Regeneration. Show all posts

Sunday 10 March 2013

Brent Planning: Incompetence or Corporate Cover-up?

This Guest Blog by local historian Philip Grant is longer than usual but raises some fundamental issues regarding planning that merit full exposition.

If you are interested in how Brent’s local government works in practice, I invite you to consider this case study. Although I have asked the question, I will leave you to decide the answer. If you wish to leave a comment, please do. You can comment anonymously, but it would help if you could give some (genuine) information, so that other readers know whether you are a “Willesden Green resident”, a “public relations consultant from Winchester”, a “Brent Council insider” or an “unconnected outsider”.

At a special Planning Committee meeting on 21 February, consent was granted to an application in the name of Galliford Try Plc to redevelop the Willesden Green Library Centre. On 22 February I lodged a complaint with Brent's Chief Executive that there had been a breach of Brent's Planning Code of Practice at that meeting. This breach was the failure to make available for inspection at the meeting the public register in which the Planning Officers reporting on the application should have declared a "prejudicial interest", so that the decision was taken without the committee being aware that the report, and the recommendation which they accepted, might not be impartial. I made it clear that my complaint was about the actions of Council Officers; I was not criticising the Planning Committee members in any way. Councillor Ketan Sheth had chaired the meeting in an exemplary way, treating all parties fairly and with great courtesy.

Brent’s Planning Code of Practice is part of the Council’s Constitution. It ‘seeks to ensure that officers and members consider and decide planning matters in an open and transparent manner’, and sets out rules which are intended to make sure that planning decisions are not only made fairly, but that they are seen to be made fairly. Item (or rule) 12 says:

12. If any officer of the Council who is involved in making recommendations or decisions on planning applications has had any involvement with an applicant, agent or interested party, whether or not in connection with the particular application being determined, which could possibly lead an observer with knowledge of all the relevant facts to suppose that there might be any possibility that the involvement could affect the officer's judgement in any way, then that officer shall declare a prejudicial interest in the public register held by the Director of Regeneration and Major Projects and take no part in the decision making process. The declaration of such interest shall also be recorded in the minutes of the meeting. This public register to be available for inspection at Planning Committee meetings.

The complaint was not some "trumped-up" delaying tactic or "sour grapes" on my part. As Brent was in reality a “joint applicant” with Galliford Try in the plans for the new Cultural Centre, I had first raised the question of the need for any of Brent's Planning Officers reporting on this proposed development to declare a "prejudicial interest" in the public register, with Brent's Chief Planning Officer, Chris Walker, as far back as May and June 2012, in respect of the initial application which was later withdrawn. I had reminded him and his Area Team Manager, Andy Bates, of this a few days before 21 February.

I had also alerted the Democratic Services Officer responsible for the Planning Committee meetings of the importance of this matter, and that I would wish to inspect the public register a few minutes before the meeting. At around 6.45pm on 21 February I had approached this Officer in the Committee Room, introduced myself, and asked to see the public register. He gave me conflicting reasons as to why the register was not available to view, one of which seemed to be that no such register existed, another that it was only available to view online and a third that it was kept at Brent House, and that I would have to make arrangements to view it there. I asked him to inform the Chairman, at the start of the meeting, about the absence of the public register, and that it was important for the business of the meeting that it should be available. He did not do so.

When it was my turn to speak, as an objector, I took the opportunity to say that the public register of Officers' prejudicial interests should have been available to inspect at the meeting, and that Mr Walker and Mr Bates should have signed it. Later in the meeting Councillor Mary Daly asked the Chief Planning Officer for his comments on the points I had raised. Mr Walker did not refer to the public register or to "prejudicial interest", but did say that his department took care to separate staff dealing with planning applications from those who were giving advice to colleagues in Regeneration and Major Projects on proposed schemes. He also said that no one could tell him what to recommend in terms of planning matters. The committee’s Legal Advisor stayed silent on the Code of Practice points throughout the meeting.

My complaint was passed to Fiona Ledden, Brent’s Chief Legal Officer and the Council’s Monitoring Officer for ensuring that all its planning procedures are carried out properly, to look into and reply to me. If he considers it appropriate, Martin will have added links below to pdf versions of her letter to me 1 March and my reply of 2 March to her, setting out our respective views. Please feel free to read them if you are interested, but I will summarise the main points as follows:

It is Fiona Ledden’s view that:

1.   Chris Walker and Andy Bates do not have an “involvement” with Andy Donald, Director of Regeneration and Major Projects. They just happen to work for the same Council department.
2.   Because of the Separation of Powers between the Planning and Regeneration sides of the department, there is no real possibility that the report to Planning Committee could be anything other than totally impartial.
3.     She agrees 'that as a matter of good practice the Public Register should have been available at the Committee meeting for inspection', but does not consider that this had any effect on the Committee's decision.

It is my view that:

1.    Messrs Walker and Bates should have declared a "prejudicial interest" in the register (it is possible that they did, but without seeing it I can't be sure) because their "involvement" with Andy Donald, and his with the WGCC project, might possibly have affected how they wrote the report and recommendation.
2.      Applying the proper tests for "prejudicial interest" it is clear from the actual report that there were parts which were not impartial. This, coupled with their "involvement" (although they may not have taken part in discussions with the Regeneration Officers, they have been working together in Brent House for the past year with colleagues who were promoting the scheme and expecting it to be approved, and their boss was the man responsible for "delivering" this project for Brent Council), means that item 12 of the Code of Practice must apply.
3.      The public register of prejudicial interests is supposed to be available to inspect at each meeting of the Planning Committee, but it was not and members were not made aware of the key information it should have contained. Reports to committee have to be impartial, and the committee are generally expected to accept the Planning Officer’s recommendation. Had they been aware that this report might not be impartial, they would have considered it in a more critical way. As a result, their decision cannot be seen to have been made fairly, which is the whole point of Brent’s Planning Code of Practice.

Another important part of Brent’s Planning Code of Practice is item (or rule) 1, which puts in formal terms another of its stated purposes: ‘The provisions of this code are designed to ensure that planning decisions are taken on proper planning grounds’. Item 1 says:
1. Members of the Planning Committee shall determine applications in accordance with the Unitary Development Plan [now the adopted Local Development Framework] unless material considerations indicate otherwise.
As the committee need to know whether applications meet Brent’s adopted planning policies, and if they do not whether there are “material considerations” which mean that an application should still be accepted, you would expect the Planning Officer’s report to contain this sort of information. The report on the Willesden Green Library Centre application was noticeably lacking in such details. I will illustrate this using the issue of open space as an example.

The Officer’s report to the 21 February meeting on application 12/2924 included a list of 22 issues on which objections had been raised, including these on open space
OBJECTIONS
The principal issues that have been raised are set out below:

2. The new building would lose the sense of openness towards the front of the site that the existing building provides for.
3. The loss of the open space to the front of the existing library is unacceptable in itself. It is well used by the community. The proposed open space is hidden around the back of the new library building and will not be welcoming.
I had actually sent a detailed letter about the open space issues to Planning Case Officer, Andy Bates, on 13 January. I summarised in an online comment, which can be seen on the Brent Planning “view comments” webpage for application 12/2924. Here are some extracts:

14/01/2013: BRENT'S PLANNING POLICY SAYS OPEN SPACE SHOULD BE PRESERVED - The development proposals contained in this application, to build the new Cultural Centre over that open space, go against policy CP18 in the adopted Core Strategy of Brent’s Local Development Framework and against policies set out in Chapter 7 ("London's Living Places and Spaces") of the 2011 London Plan. / This local open space was created as part of the Willesden Library expansion scheme in the 1980's, as one of the policy commitments given by Brent Council in the Willesden Green District Plan, adopted in December 1980. / The District Plan identified the site which Brent Council was then acquiring for its new Library Centre as the ideal location for a variety of new community facilities. The plans which were then drawn up for those facilities, in full consultation with the local community, included this 'much-needed open space' on the Willesden High Road side of the Library Centre. / Part 5 of Brent's 2010 planning Core Strategy shows that the area around the High Road in Willesden Green is still an area of open space deficiency, and says that local open space in such areas is 'crucially important to the borough' and in 'need of protection'. That is why core policy CP18 says 'Open space ... of local value will be protected from inappropriate development and will be preserved for the benefit, enjoyment, health and well being of Brent's residents, visitors and wildlife.' / It is clear that the proposals in the planning application to build over the open space in front of Willesden Green Library Centre would be 'development harmful to its use and purpose as open space', so that the open space should be preserved. 

The summary of objections did not reflect the planning policy points I had made, so what did the main body of the Officer’s report say on these matters? These are the main extracts:

FACILITIES OUTSIDE THE BUILDING

The development proposes to change the current open areas around the building – principally by providing the new ‘Brondesbury Walk’ and improvements to the public realm in Grange Road. / The range of current outside areas includes the space to the rear of the library, the small children’s play area adjacent to it and the space to the front of the library building./

The application scheme creates a new street entitled ‘Brondesbury Walk’ to the rear of the new library which provides a single space larger than any of the single areas that exist at present. However, the space would be some 65 square metres smaller than a combination of the existing space to the rear and the open area to the front (total 565 square metres rather than 625 square metres). This small reduction is acknowledged. However, in qualitative terms it is considered that the proposed spaces will, at least, be equal to the existing offer.... / The intention is that the space will be used as a new local square for use by existing and future communities. It will be predominantly hard paved, but will include mature trees to provide visual interest and shade. The level change between the WGCC and the residential Block A will allow for a double terrace of seating to be provided for visitors of the Centre to use. /

It is proposed that the new WGCC building will sit in a sensitively interpreted civic space which will provide a high quality setting for the building. The spaces will not only provide formal civic amenity, but interesting play facilities making the public space around the centre as much of a destination as the building. The quality of landscape interpretation, including the use of level changes, has allowed a sensitive designed progression from the civic public spaces adjacent to the Cultural Centre to the semi-private and private areas of the residential development behind.

There was still no mention of Brent’s core policy CP18, an admission that there would be a smaller area of open space of at least equal quality ‘to the existing offer’, but a claim that it would be a better ‘civic space’, which presumably is regarded as a “material consideration”. If the report had stated that the application’s proposals on open space went against Brent’s planning policies, but had then set out a clear argument as to why the benefits of the new scheme were considered to outweigh those policy considerations, then it might have been considered even-handed. However, I can see no valid reason why core policy CP18 was not brought to the attention of Planning Committee. 

The report also failed to mention that the main function of the top level of “Brondesbury Walk” is to provide pedestrian access and natural light to one side of residential Block A (which will be built right up to the edge of the land which Brent is giving to Galliford Try in return for the developer constructing the new Cultural Centre). Another factor making the proposed new open space even smaller is that its western (Grange Road) end must be kept clear, to allow lorries servicing the Cultural Centre to reverse into “Brondesbury Walk” in order to turn round.

The open space issues are just one of a number of areas where clearly identified failures to comply with Brent’s planning policies, which were brought to the attention of Planning Officers, have not been properly reported to Planning Committee in this case. The Officers' report can hardly be claimed to be impartial in these circumstances. Add to this the strong case as to why those Officers should have declared a “prejudicial interest” in the public register, and the failure to have that register available for inspection at the Planning Committee meeting, and I hope you can see why I felt it necessary to complain about the apparent breach of Brent’s Planning Code of Practice. 

Was what has happened the result of incompetence, a corporate cover-up or was there nothing wrong at all with the actions of Council Officers? Fiona Ledden is a trained lawyer, and I am not, so it is possible that I may have misunderstood how the Code is meant to work in practice. What do you think?








Friday 14 December 2012

Willesden Town Square Enquiry adjourned until February 2013

Cllr Muhammed Butt addresses 100 Days Of Peace Rally in the Town Square
 The Public Enquiry into the application to register the space outside Willesden Green Library as a Town Square  has been adjourned until February 2013 on the grounds that the applicant was not given enough time to prepare the case.

A preliminary hearing will be still be held on Monday December 17th, 10am Studio 2, Willesden Green Library Centre. This will hear directions from the Inspector to the parties concerned. The meeting is open to the public.

The delay has implications for the timetable for the planning application for redevelopment of the site and the building of 95 homes as the developer's plans involves building on the Town Square.

Evidence of the use of the Town Square can therefore continue to be sent to Martin Redston mredston@compuserve.com as signed PDFs with any photographic evidence. The Inspector will be seeking to establish that:

i. A significant number of inhabitants of any locality, or any neighbourhod within locality, indulges as of right in lawful sports and pastimes on the land for a period of at least 20 years; and
ii. They continue to do so at the time of application


Comments are also still possible on the planning application and can be sent to andy.bates@brent.gov.uk (Reference 12/2924 12/2925)

Wednesday 14 November 2012

Willesden Town Square Inquiry to be held by independent Inspector

The French Market on part of the proposed Town Square
Brent Council has decided to to appoint an independent Inspector to conduct a non-statutory local inquiry in the application for the plaza between the current library and  the now closed bookshop, and the Victorian Library, to be designated a Town Square.

The decision was made on the basis that it will be a simpler and clearer process if the Town Green/Square application was decided before the library redevelopment planning application goes to Planning Committee. If  planning permission had been granted before a successful Town Square registration then the planning consent could not be implemented. This is because the plans submitted by developers Galliford Try build on the space concerned to make room for  the building of flats to the rear of the new building.

An Inspector has been appointed and is expected to hold the local inquiry in the week commencing 17th December 2012. Currently the closing date for comments on the planning application is December 6th 2012 but this is subject to revision.

Monday 12 November 2012

It ain't over 'til the wrecking ball swings

On Saturday I received a letter from  the Brent Planning Department informing me that Galliford Try PC has submitted planning applications to Brent Council (12/2924 and 12/2925) for the redevelopment of Willesden Green Library.

The letter gave a period of 21 days from the letter date of November 8th 2012 for receipt of comments. However it also said that plans 'should' be available on the council website 'by 13th November'. I have written to Brent Planning Department to say that it is not possible toe to comment on plans that are not available and asked for confirmation that the 21 days will run from the date that they are  uploaded to the planning portal on Brent's website.

You would think that after all the controversy over the demolition and regeneration that the council would try and get this right.  Perhaps the rush to get this unpopular project on the road by January has led to yet another decision that will alienate the local community unnecessarily. Unless it is of course aimed at giving Keep Willesden Green campaigners and local residents as little time as possible to comment on extremely detailed plans. Surely they have more respect for local electors than that?

Link to Planning Application

6.20pm on Monday: I have received the following  response from Andy Bates at Brent Planning about the planning deadline.
Dear Mr Francis, 

I am writing to confirm that the applications will be advertised in the same way as the earlier submissions (press and site notices) and, as a result, the 21 day consultation period will always expire 21 days after the last consultation takes place. In this case, this is likely to be the press notice. My Colleagues in Planning Technical support tell me that this Notice is likely to appear at the end of this week, so the period you are querying will be 21 days from then. 

The intention would be to get to the planning applications to the earliest Planning Committee that would be in a position to consider the proposals. I would imagine that this would be likely to be in January/February 2013.
 
I would argue that this is only fair if the plans are on the website by publication day which is November 15th for our two main local newspapers.

Sunday 1 April 2012

Navin Shah backs retention of Old Willesden Library

Close behind Ken Livingstone's distancing from Brent Labour's library closures the Labour AM for Brent and Harrow, Navin Shah, has told a constituent that he favours the retention of the Old Willesden Library on local heritage grounds:
With regards to Willesden Green Library, as an architect by trade I feel preserving Willesden Green Library is extremely important. In Harrow, I have fought long campaigns to keep locally listed buildings and am on the board of Harrow Heritage Trust, which take matters such as these extremely seriously. I want to keep Willesden Green Library building and am actively pursuing this issue.
Shah's full statement can be read on the Keep Willesden Green blog HERE


Friday 9 March 2012

Big push on Willesden Green tomorrow

The Keep Willesden Green campaign has had excellent coverage in the Brent and Kilburn Times this week. They will be out in force tomorrow for the Brent Council-Galliford Try Exhibition at Willesden Green Library.

Campaigners are pushing to get 5,000 signatures on the petition to save the historic Old Willesden Library building from demolition. Reaching 5,000 will mean that the issue has to be discussed at full council. E-petiton is HERE and the paper version will be outside the Library tomorrow morning and lunchtime.

The main issues are summarised in the video below: