Saturday 22 July 2023

Brent’s Wembley Housing Zone – 'Some' Good News! (But what is Brent Council's policy now on unaffordable Shared Ownership?)

Guest Post in a personal capacity by Philip Grant 

 

Architect’s view of Brent’s 250 home Cecil Avenue development.

 

On 14 March this year, Martin’s post “Wembley Housing Zone: Never mind the gloss – what are the details?” shared with us a Brent Council press release, about its deal with Wates to finally build the 250 homes at Cecil Avenue, which it had received full planning consent for in February 2021. The blog included “links” to several of the guest posts I’d written since August 2021, urging the Council to include more genuinely affordable homes for rent in the project, especially homes at Social Rent level which the 2020 Brent Poverty Commission said should be the priority.

 


My “parody” Brent Council Homes publicity photograph (from November 2021).

 

Since 2021, Brent’s plans had been to allow its “developer partner” to sell 152 of the homes on the former Copland School site privately, with only 37 of the 250 for London Affordable Rent, and the other 61 as “intermediate” Council housing (either shared ownership or Intermediate Rent level). 

 

You would have thought that when they arranged additional funding from the GLA, to allow for more affordable homes to be delivered as part of this Wembley Housing Zone project, Brent would have celebrated with another press release, telling us about this “good news” story. Instead, I only discovered it when I spotted an item on the Forward Plan page of the Council’s website, as I was checking whether another item had been included there. It was about a Key Decision made by the Corporate Director, Communities and Regeneration, in April 2023:-

 



There was a “Officer Key Decision Report” on the website, but (true to form) the appendices to it were both “exempt”, so that the press and public were not allowed to find out ‘information relating to the financial or business affairs of any particular person (including the authority holding that information)’. The Report did, however, give an outline of what the amended agreement with the GLA involved:-

 


 

My various attempts, since August 2021, to get Brent to include more genuinely affordable homes at Cecil Avenue, using additional GLA funding where possible, have been ignored, dodged or blocked. I was told that anything other than what the Council already planned would be impossible, because the scheme would not be viable. Now they had an extra c.£10.5m, how many extra affordable homes would they be able to provide? 

 

I had to submit a Freedom of Information Act request to find out, but “Wembley Matters” can (at last) share the Good News!

·      Instead of only 37 of the Cecil Avenue homes for London Affordable Rent, there will now be 59. 35 of these will be family-sized (3 or 4-bed) homes.

·      36 of the Cecil Avenue Council homes will be for Shared Ownership (of which 9 will be family-sized).

·      3 of the Cecil Avenue Council homes will be “Other” affordable homes. (Does that mean at Intermediate Rent?)

·      As before, 152 of the homes being built by Brent Council at Cecil Avenue will be for private sale by Wates (including 20 family-sized).

My title does say ‘Some Good News’. The other part of the Wembley Housing Zone project, across the road at Ujima House, was meant to have ALL of its 54 flats for London Affordable Rent to Council tenants. The revised figures for this block are now:

·      32 for London Affordable Rent (including all 8 family-sized flats).

·      22 for Shared Ownership.

So, the original proposed number of Wembley Housing Zone London Affordable Rent homes was 91 (37 + 54), and the revised number is 91 (59 + 32). Perhaps that is why Brent did not want to draw attention to the extra funding they’d negotiated from the GLA!

The only improvement from the extra GLA funding, and that is genuinely to be welcomed, is that more of them will be family-sized homes for affordable rent, and more will be delivered earlier (Ujima House still only has the outline planning permission approved in February 2021).

Of the original proposed 61 “intermediate affordable homes”, 58 have now been positively identified as being for shared ownership. But didn’t Brent’s Cabinet, just last week, decide to sell off the 23 shared ownership homes it had acquired at the Grand Union development,  because the Council does not have 'the knowledge, experience and the capacity to effectively sell and manage' shared ownership homes?

 

Placard from a demonstration against Shared Ownership.

 

The Report to the 17 July Cabinet meeting clearly showed that shared ownership is well above the affordability level of most families in Brent, and admitted:

 

‘… the market and demand for Shared Ownership, particularly in the latter quarter of 2022 was and has remained turbulent. This is both in terms of too many shared ownership homes available in the market and appetite and demand for these homes reducing.’

 

In a November 2022 guest post, I set out the reality of Brent’s Affordable Council Housing programme, and why they should not include any shared ownership homes. But the decision makers at the Civic Centre are still pressing on with their flawed policies!

 


Cllr. Shama Tatler fronting a publicity photo at the Cecil Avenue site in March 2023.

 

Brent’s March 2023 press release about its Wembley Housing Zone deal with Wates began by claiming: ‘More much-needed housing will soon be a reality following an agreement to build 304 new homes in Wembley.’ From the hard hats and “high-vis” jackets in the photograph that came with it, you might believe that heavy machinery was already at work on the Council-owned Cecil Avenue site, which has been vacant for at least three years.

 

 

The Cecil Avenue site from the top deck of a bus, 26 June 2023.

 

In the extract from the April 2023 Key Decision Report above, it says that ‘start on site [was] recorded on 27 March 2023’. When I went past on the last Monday in June, there was no machinery, no workers and no progress on the Cecil Avenue site, just two portacabins. My recent guest post, 1 Morland Gardens – an Open Letter to the Mayor of London, explains what is required for a “start on site” for GLA funding, and it appears this has not yet happened.

 

It appears that the ‘will soon be a reality’ actually means ‘by 31 December 2026’. Some eventual good news, but I still believe that Brent could have done so much better than 59 “genuinely affordable” homes for rent to Council tenants as part of its 250 home Cecil Avenue development.

 


Philip Grant.

Tuesday 14 March 2023

Wembley Housing Zone: Never mind the gloss - what are the details?


 Impression of the Cecil Avenue blocks, High Road, Wembley

 

Brent Council’s press releases are notable for what they leave out as much as what they include. The latest heralding new homes on the Cecil Road, Wembley site (formerly Copland School) and Ujima House on the other side of the road (See PR below) leaves out vital information pursued by Philip Grant in several guest posts on Wembley Matters.   LINK  LINK

 

 Brent Council received planning permission for this development more than two years ago (February 2021). On the latest information only 37 of the 250 homes at Cecil Avenue will be for London Affordable Rent (LAR), and the 54 LAR homes promised for the Ujima House site (which still only has outline planning permission) are not expected to be delivered until 2026.

 

The Wembley Housing Zone scheme is Shama Tatler's responsibility - she talks it up in the press release. Cllr Tatler and Muhammed Butt must bear the blame for the details and delay over the provision of these home.

 

Reacting to the Council press release on Twitter this morning Cllr Anton Georgiou (Lib Dem Alperton) asked:

 

Will these be Council homes for Council tenants? Genuinely affordable family homes? Or more of the same? We need answers and clarity, not just headline figures.

 

The Brent Council Press Release

 


Deal signed to deliver more than 300 new homes in Wembley

More much-needed housing will soon be a reality following an agreement to build 304 new homes in Wembley. 

 

A deal was signed this week between Brent Council and Wates to deliver 250 homes on land east of Cecil Avenue, which had previously been the site of Copland School. The plan is for a high-quality, mixed-tenure courtyard development of five to nine storeys with one-bed, two-bed, three-bed and four-bed apartments and maisonettes. The new development will also house commercial units and community floorspace at street level.

 

Opposite this site at Ujima House, another 54 homes will be built, along with workspace units, including a café at street level.

 

A total of 152 homes will be made available for private sale on the Cecil Avenue site. The other 152 properties on both Cecil Avenue and Ujima House will be a mixture of affordable homes for council tenants and people on middle incomes.

 

Councillor Shama Tatler, Cabinet Member for Regeneration, Planning, and Growth, said: 

 

“This is fantastic news for residents of this up-and-coming area. The vision is to revitalise the eastern end of the High Road of the town centre, linking the established Wembley Central to the new Wembley Park neighbourhood emerging around the stadium.”

 

Designated and partly funded by the Mayor of London, the Wembley Housing Zone aims to create new homes and jobs, new leisure, retail and workspaces, public realm improvements and increased accessibility for pedestrians, cyclists and road users. 

 

Nick Williams, Regional Managing Director at Wates, said: “Our guiding principle is that everyone deserves a great place to live, and these modern new homes will be warm, comfortable and safe to live in. Not only that but we will be working with the local community to deliver these mixed-tenure homes. This means employing the services of local businesses and people along the way to help regenerate the area and inspire a new community.”

 

The new development agreement represents another opportunity for Brent Council and Wates to collaborate. The two organisations are currently working together to create 99 new council homes at Church End and have recently successfully delivered 149 homes at Knowles House and Anansi House. 

 


 

Friday 13 January 2023

Brent’s Wembley Housing Zone contract award – still too many secrets!

 


Guest post by Philip Grant in a personal capacity

 

In a guest post last month (‘Tis the Season to be Sneaky!) I suggested that Brent Council might be trying to use its “urgency procedures” to get the decision to award a major contract for its Wembley Housing Zone (“WHZ”) development slipped through over the Christmas / New Year period, in the hope of avoiding it being called-in for scrutiny.

 

Although the decision was scheduled to be made on 19 December, it wasn’t officially made, by Brent’s Chief Executive, until 10 January, and published on the Council’s website the following afternoon. Normally, 28 days clear notice of a Key Decision has to be given, but the Urgent Key Decision Form sent to a Scrutiny Committee Chair on 12 December said that was not possible. Yet the decision was made 29 days after “urgency” was claimed!

 

Part of the Evaluation Process section from the Officer Key Decision Report.

 

In fact, notice of a Key Decision for this contract could have been given at least several months before 12 December. The Officer Report (undated), on which the decision to award the contract was based, says that the tender process started on 30 April 2022, when the Council advertised for initial expressions of interest from contractors. Eight had provided the necessary responses by the closing date of 31 May. The four short-listed contractors were invited, on 3 July, to submit tenders, and three had submitted valid tenders by the closing date of 18 October.

 

The Recommendation from the Officer Key Decision Report.

 

After all of the evaluation of the tenders by Council Officers, the recommendation which Brent’s Chief Executive accepted was to award the “developer partner” contract to Wates Construction Ltd, for a price of £121,862,500. That is a lot of money! In fact, the report shows that it could be even more than that, perhaps as much as £133m (and that is after an estimated £4m already having been spent on architects’ fees).

 

Extract from the Financial section of the Officer Key Decision Report.

 

It appears that the £126.5m will be the cost of building 304 homes on two sites which Brent Council already owns. That is a building cost of around £416,000 per unit. As para. 4.2 in the Report extract above states, part of this will be funded through capital receipts from the sale of private homes. When Cabinet agreed this scheme in August 2021, it included allowing the development partner to have half the homes (152, and all on the more favourable Cecil Avenue site, which will be completed first) to sell privately, for profit. How much will Wates be paying Brent for those homes as part of the contract deal? We don’t know – it’s a secret!

 

Part of the funding will also come from the ‘capital receipts from … intermediate homes’. In plain English that means the sale of percentages in shared ownership flats within the 152 homes that the Council will own. In August 2021, Cabinet agreed that 61 of the 98 homes which Brent would retain on the Cecil Avenue site should be “intermediate”, with only 37 of them for London Affordable Rent. Following the November 2022 Cabinet meeting, will the figure of shared ownership be increased?  We don’t know – it’s a secret!

 

Wembley Housing Zone extract from the “Affordable Housing” report to Cabinet, 14 November 2022.

 

Martin published a guest blog I had written about that Affordable Housing report to the November 2022 Cabinet meeting, and another which I wrote following the Council Leader’s response to questions which Cllr. Anton Georgiou had asked at that meeting. I showed that there is already a surplus in shared ownership homes on offer in Brent, which is likely to continue and increase, and that shared ownership is not really affordable to most people in housing need in Brent. So why is the Council planning to make many of the WHZ homes shared ownership, which won’t help the people its affordable homes policy is meant to house?

 

Outline of the contract from the Officer Key Decision Report.

 

The contract, as shown by the extract above, is in several parts. This is because although both WHZ sites were given planning permission in February 2021, Ujima House only has outline permission. Because of the long delay in getting to the contract award stage (which has greatly increased the cost of the project), the “developer partner” has to prepare, submit and get approval for the actual Ujima House plans. That’s why there is a completion date of 31 December 2026 (nearly 4 years away!), with a possible extension, for those homes to be delivered.

 

The former office block at Ujima House still has some “meanwhile” occupants, including the thriving Stonebridge Boxing Club, a vital resource for the local community. They have still to find an alternative home. Despite the long lead time before any work at Ujima House can begin (apart from its possible demolition, leaving an empty site, like that of the former Copland School buildings, where work on the Cecil Avenue homes could start straight away), Brent Council wants to ‘seek to assist them in finding suitable alternative premises’ (evict them a.s.a.p.). 

 

Extract from the Equality Implications section of the Officer Key Decision Report.

 

The Report’s determination ‘to ensure a start on site by the end of March 2023’ must mean that the extra £5m funding the Council has obtained from the GLA comes from its 2016-2021 (but extended to 2023) Affordable Housing Programme. There is probably some “spare” money in that pot because Brent will fail to start some of its other New Council Homes projects before the 31 March deadline! The £5m looks like the grant for 50 London Affordable Rent homes, at £100k per home. The Cabinet’s August 2021 decision (possibly since watered down) was for all 54 homes at Ujima House to be for LAR, but only 37 at the Cecil Avenue site, so at least some of the latest GLA agreement must relate to Ujima House.

 

One final point. The documents published with the decision notice include the Council’s Tender Evaluation Grid, where Wates appear as contractor “C” (the identities of “A” and “B” are secret). Although “C” scored highest overall, because their Financial score was much better than the other two (meaning their price was lowest), they were only second in the Quality section. Their Quality score was 68.6 out of 100 (contractor “B” was best with 72.0). Brent has had problems over poor quality housing developments in recent memory.

 

The Quality section of the WHZ contract Tender Evaluation Grid.

 

Non-Cabinet councillors have five working days to call-in the Key Decision for scrutiny, if they consider there are reasonable grounds to do so. As it was published on 11 January, at least five members would need to call-in the decision by 5pm on Wednesday 18 January for the award of the contract to be put on hold, so that (probably) Community and Wellbeing Scrutiny Committee could consider it. It will be interesting to see whether that happens!

 


Philip Grant.

 


Thursday 22 December 2022

‘Tis the Season to be Sneaky! Is Brent trying to award the c£100m Wembley Housing Zone contract without scrutiny?

 Guest post by Philip Grant in a personal capacity

 

The location of the two Wembley Housing Zone sites.

 

If you’re a regular reader of “Wembley Matters”, you will be aware of Brent’s often repeated statements about the urgent need to build more Council homes for the families in temporary accommodation and on the waiting list. They are used to justify the Council’s often unpopular “infill” plans for some of its housing estates, and by Brent’s planners to justify recommending applications that breach some planning policies, and are seen by many as overdevelopment.

 

You will also be aware of Brent’s promise (and Labour Group election pledge) to build 1,000 genuinely affordable Council homes in the five year period ended 31 March 2024.

 

If you’re a regular reader, you will have seen at least some of my previous guest posts about Brent’s Wembley Housing Zone proposals. These include building 250 homes on the Council-owned brownfield site of the former Copland School building at Cecil Avenue. If they had got on and built them as soon as they had full planning permission in February 2021, that could have contributed a quarter of the 1,000 homes target. But as a result of a Cabinet decision in August 2021, 152 of those new homes are to be built for private sale at a profit by a “Developer Partner”. 

 

Title page to the Report which Cabinet approved on 16 August 2021.

 

For much of 2022, I tried to get this (what appeared to be an odd) decision properly scrutinised, but that was finally scuppered by the Chair of the Resources & Public Realm Scrutiny Committee (acting on whose instructions?) in September. Now there appears to be an attempt by those in power at Brent Council to stop any scrutiny of the actual award of the contract for the Wembley Housing Zone scheme.

 

This will be a very big contract, likely to be worth in excess of £100m. Brent advertised in April for expressions of interest from contractors for this, and they had to respond by the end of May. In November, Cabinet were informed that progress had been made, but the details were hidden away in an “exempt” appendix to the Report.

 

Extract from the November 2022 “Update on the Supply of New Affordable Homes” Report.

 

Then, in the past few days, an item appeared on the Forward Plan page, saying that the decision to award the contract, to be Brent’s Developer Partner for the Wembley Housing Zone scheme, would be made this month, under ‘urgency procedures’!

 

The Forward Plan entry from Brent Council’s website.

 

As Brent has been working towards this decision since August 2021 (in fact, long before that) and the contract procurement process has been going on for over six months, why was it urgent and what are those procedures? There are some clues from the document, dated 12 December, that was provided in a “link” from that Forward Plan, which I will ask Martin to attach a copy of at the end of this post, for general information.

 

It appears that there are various degrees of urgency. Normally, at least 28 clear days’ notice of a Key Decision has to be given. In this case, although it would be less than 28 days, it was planned to be ‘at least 5 clear days’ notice.’ The decision would be made on 19 December.

 

Extract from the Urgent Key Decision form.

 

If it had been less than five days, the Chair of a Scrutiny Committee would have ‘to agree that the decision is urgent and cannot be reasonably deferred for the reasons detailed ….’  But as it was ‘at least 5 clear days’, ‘the Scrutiny Chair is only required to note that the decision will be taken.’ In other words, there would be no scrutiny of whether or not the decision was actually urgent.

 

According to the Urgent Decision form, 28 days’ notice could not be provided because: ‘Conclusion of the contractor developer partner procurement was delayed.’ But Council Officers have been working on that procurement for months, and would have known that a decision on it would be required at some time in the near future, so notice could surely have been given earlier.

 

And the reason why it is ‘impractical to defer the decision to a later date’ is said to be ‘to meet delivery timescales and funding conditions.’ With the delays which have already occurred since Brent first entered into its Wembley Housing Zone agreement with the GLA in 2015, delivery timescales don’t seem to have been much of a priority before. As for funding conditions, the Council must have been aware of these ever since funding agreements were made (at least 15 months ago for the extra £5.5m the GLA agreed to offer).

 

As at 6.30pm on Wednesday 21 December the formal decision has not been published on the Decisions page of Brent Council’s website. Perhaps it will be published on 22 or 23 December. But why would Senior Council Officers (and the Cabinet member responsible for this project, who is the Lead Member for Regeneration, despite this being mainly a housing development) delay making the decision, and giving the intention to make it so little publicity, until just before the Christmas / New Year holiday period?

 

Why Call-in matters, from Brent’s Protocol on Call-in.

 

I’ve said before that those behind this controversial Wembley Housing Zone project want to avoid any scrutiny of it. The award of the contract is a Key Decision, so could be called-in for scrutiny. I may be wrong, but I suspect that the decision is being made now to minimise any chance of a call-in. For call-in to take effect, at least five backbench councillors (non-Cabinet members) need to request that a Key Decision is called-in, and they need to do so ‘within 5 days of the date on which the record of the decision is made publicly available.’ 

 

How many councillors, if they were not aware that this important Key Decision was about to be made (because the usual 28 days’ notice has not been given) would be looking at the Decisions page on the Brent Council website over the holiday period? And even if any of them were keeping an eye on it, what would be the chances of organising five members to complete and submit call-in request forms before the end of the fifth day?

 

That’s the main reason I’ve asked Martin to consider publishing this guest post – so that this Festive Season is not used as a cover to sneak through a Key Decision without anyone realising that has been done until it is too late!

 

Philip Grant