Showing posts with label Bridge Road. Show all posts
Showing posts with label Bridge Road. Show all posts

Tuesday, 19 October 2021

Some improvement for pedestrians at dangerous Bridge Road/North End Road junction

 

AFTER


Following concerns registered by Wembley Matters and other Brent residents,  the issue of pedestrian safety at the junction of the New North End Road extension and Bridge Road was taken up by local councillor Gaynor Lloyd.

Now bollards have replaced some of the Hostile Vehicle Measures (HMVs) blocks that were on both sides of North End Road.  The remaining blocks on the west side were moved back this weekend giving better access to the tactile dropped kerb to wheelchair users, people with buggies and the sight impaired.

It is a slight improvement but there is an urgent need for pedestrian controlled lights and signal improvement for vehicles and cyclists.

Wednesday, 4 August 2021

Brent Council responds to concerns over pedestrian safety at new North End Road,/Bridge Road junction in Wembley Park

Brent Council has responded to concerns that I expressed on behalf of residents over pedestrain safety at the new North End Road/Bridge Road junction opposite Wembley Park tube station.

I wrote:

There has been quite a lot of concern expressed on social media about the safety of the new junction at North End Road/Bridge Road and particularly the problems facing wheelchair users and parents with large buggies when crossing.  The tactile paving on the Olympic Way side is blocked and the several gaps between the blocks cause pedestrians to move in several directions and children sometimes separate from their parents. There are no lights or other controls. It is particularly difficult for those who are partially sighted or blind.

Could you clarify, so that I can pass the message on, whether the council or TfL will be adding any lights etc to the crossing/junction and whether the blocks are temporary or a permanent hostile vehicle prevention measure.

I attach a link to a video taken today (July 29th) around 3pm - not a busy time.

 

This is the Council's response received yesterday:

Thank you for your email and video link relating to safety concerns that have been raised about the new junction, particularly with access for wheelchair users and parents or carers with pushchairs and buggies.

 

The concrete barriers are temporary security measures and they will be replaced by bollards. Unfortunately, there was a delay in delivery from our supplier, but I am pleased to inform you that work has now been programmed for 23rd August. In the meantime, our contractor has moved the Give Way sign post from between the concrete barriers so that it no longer impedes pedestrian access.

 

As this is a new junction, we will of course be monitoring its performance and will consider whether any further improvements are necessary.

 

We are currently liaising with Transport for London on signalising the junction in the future, this will improve amenities for pedestrians.

 I have not yet had a reply from Brent Highways or TfL on whether buses will be able to use North End Road on event days as planned. It has a weight limit of 7.5tonnes.

 

Sunday, 13 June 2021

New North End Road/Bridge Road junction at Wembley Park now in operation

 

North End Road junction with Bridge Road

I was alerted to the opening of the North End Road/Bridge Road connection yesterday (thank you Amanda) and popped down this morning to check it out before the football crowds got going. There are no lights at the junction at the moment so ard drivers and pedestrians were a little confused. It may have got more confusing at later when the crowds and cars arrived.

You will see that there is a 7.5tonne weight limit at the junction. My questions to Brent Council Highways and Transport for London on how that will affect plans to divert buses down North End Road on event days have gone unanswered,

Asd you will see the gradient of the new section of North End Road is steep and the view from the lower section of North End Road towards Bridge Road is quite restricted at driver height so difficult to see vehicles turning right from Bridge Road.


 

 

The Hostile Vehicle Mitigation Measures (concrete blocks covered in mock greenery) are very much in evidenc and being used as resting perches by visitors.

 

The steps and ramps which used to serve North End Road now just lead from Bridge Road to Olympic Way. Michaela staff and students and local residents residents now have direct pedestrian access to North End Road.

 


The former busy bus stop opposite Wembley Park station has been removed along with the bus stopping place. As you can see more Hostile Vehicle blocks have been installed where the buses used to stop.  This means that passengers will continue to have to wait on the narrow strip of pavement outside the Bridge Road shops - not ideal for social distancing.



Tuesday, 11 May 2021

Wembley Park road changes update

 

A glimpse of the new Bridge Road- North End Road junction. At present it is a steep ramp but aggregate was being delivered this morning presumably to reduce the gradient. There are  reports that there will be weight restrictions when it opens. Brent Council has said it should be open to pedestrians by the end of the month.

The mural on Olympic Way is covered again apart from one section but correspondence is still taking place over whether planning permission for advertising is actually in place.

Behind the ramp on the right is 1 Olympic Way, former office accommodation being converted to flats.

The length of Olympic Way up to the infamous steps is nearing completion.

 

There is no word yet on when Engineers Way will be open again to traffic. 'Hostile Vehicle Mitigation Measures' have to be put in place.


Friday, 5 March 2021

Restored Bridge Road/North End Road junction expected to open to pedestrians and local traffic in late May

 

Works taking place at present

 

A 2019 impression of the completed junction

 

In a statement to Wembley Matters, Brent Council has said that the restored junction of North End Road and Bridge Road, Wembley Park, is expected to open in late May:

We are working hard to complete the works as soon as possible. It is a complex project and there was an unforeseen delay due to discovery of an uncharted gas main and old pedestrian subway. However, we are working at pace to make up time and currently anticipate that there will be access from Bridge Road to North End Road from late May 2021.

 

In the meantime, the existing pedestrian diversion arrangements will remain in place, with access to Michaela School from North End Road near Victoria Halls.

 

We are in discussion with TfL about their signals programme. They are experiencing delays due to staff being furloughed, however, our current intention is to open the road up to local traffic late May.

 

Further to his comment below, local historian Philip Grant has sent me the following aerial photo, taken in 1948, which clearly shows the old pedestrian subway from Wembley Park Station that caused an 'unforeseen delay' in the work:-



Tuesday, 15 September 2020

Works on Olympic Way Bridge Rd/North End Road connection and Stadium Steps underway

Access ramp from Bridge Road to Olympic Way and North End Road on bottom left 

 
 
View of North End Road, Michaela School, Victoria Tower from access ramp (Olympic Way


Notice closing pedestrian access to ramp and stairs

Works started on Monday on the construction of the new access road and footpath connecting North End Road with Bridge Road, Wembley Park.  The notice said that the stairs and ramp would be closed to pedestrians from  yesterday but they were still open today.  The works are due for completion in April 21st 2021.

 

The view of the steps from the far end of Olympic Way

Work in progress

A view of the new steps was also available today.  They will replace the pedway as part of the £17.8m 'improvements' to Olympic Way approved by Brent Council, paid from Quintain's  Community Infrastructure contribution.


Friday, 17 July 2020

There's more to Quintain's Wembley Stadium steps than meets the eye


There is rather more to the triumphant tweet by Quintain that yesterday announced the start on work to replace the Wembley Stadium pedway with steps.  Before Quintain was taken over by the American Lone Star company in 2015 LINK , the replacement of the pedway project was announced in 2007 as (para 3) 'One of the largest pieces of privately funded public spaces in the UK.'

By the time it got down to Planning Permission, Brent Council had agreed to use Community Infrastructure Levy money, paid by developers for infrastructure improvements, towards the costs of the new steps and other Olympic Way improvements.

 Iconic?

Brent Planning Officers waxed lyrical on the benefits:
To assist in achieving the vision for Wembley, a significant element in terms of place making is the provision of new and substantial steps to the stadium to replace the pedestrian way (‘pedway’) and works to the public realm between Wembley Park underground station and the National Stadium Wembley: Olympic Way. This will enhance the area, both from an aesthetic and functional requirement.

Olympic Way as a piece of public realm is showing its age. It does not present the type of quality considered consistent with the environment necessary for a world renowned iconic venue and the wider Wembley Park development. In the context of other pressing infrastructure needs and other Council revenue spending requirements, a response might be that a significant Council funding contribution 
towards these changes should be a low priority. Nevertheless, this would be a simplistic and does not take account of all factors, including limitations associated with funding streams generated from development.

CIL funding attained by the Council is specifically related to infrastructure and is not available to support Council general revenue spending. In addition this proposed change in public realm should be seen as part of a wider picture about what will be achieved in Wembley which will have far reaching positive impacts for Brent and its prospects.
As we argued at the time there are many improvements that need to be made to Brent's infrastructure that would benefit local people more. The aesthetic argument is weak and the functional one unpersuasive - are the steps really more functional (and safer) than the pedway?

But there was something else, Brent Council did a deal with Quintain as part of the scheme, whereby Quintain agreed NOT to build on the land next to Wembley Library/Civic Centre:

Cabinet were asked to:
Confirm or otherwise the contribution of up to £12.1 million +VAT towards Zone C improvements, such contribution being contingent on Quintain: 



a.     Not pursuing development of site NW04 (see plan above) adjacent to the Civic Centre to the extent currently permitted in the parameters plans associated with outline planning permission 10/3032

b.     Working with the Council to deliver a development that better complements the role and setting of the Civic Centre, in particular creating a significant new square outside the Civic Centre Library

c.      Agreeing a business plan and agreement, between Quintain and the council, for the future sharing and reinvestment of the net income generated through assets on Olympic Way in Zones A, B and C.

d.     Securing up to one third funding contribution from Wembley Stadium owners.
So Quintain got the money partly because Brent Council did not want its building hemmed in by high rise flats.  Many councillors and staff were peeved about the high rise flats between them and the stadium., spoiling the view. 

The other part of the deal was that Brent would share in the income generated by shops, bars etc that would be built in the undercroft of the steps. Somehow or other it was thought that the steps themselves would make the estate more attractive to visitors and provide an economic bonus.



The plans hit a problem when it was announced that the owners of the Stadium were putting it on the market and it was not clear if the new owners would cough up their shares of the funds LINK  . Things were further complicated when Quintain attempted to sell off its estate LINK.

The steps were not ready as promised for Euro 2020 and did not get started but Quintain's press release promises that the steps will be ready in time for the deferred matches:
Quintain, the developer behind Wembley Park, has today started the final upgrade works to Olympic Way with the project to replace the pedestrian walkway (known as the ‘pedway’) with an iconic new entrance to the National Stadium. The centrepiece of these works is the Olympic Steps, which form the final stage of a wider package of upgrades to the length of Olympic Way. The steps will be operational in time for the Carabao Cup Final in 2021 and the UEFA Euro 2020 tournament, which will be held in June and July 2021 and hosted at Wembley Stadium.
Such speed, in the face of possible future Covid19 second and even third wave, seems optimistic, particularly when you factor in the previously published schedule of works:

The delivery of the project can be split into three main construction phases:

•       Phase 1 – Site Preparation and Substructure Works;

•       Phase 2 – Pedway Demolition and Construction of Steps;

•       Phase 3 – Landscaping and Fit Out.

.        6.62  Phase 1 - The initial work activity will focus on clearing the site below and around the Pedway of those utilities and other items that will obstruct the Pedway demolition and subsequent staircase construction. As areas become clear, works to the foundations and substructure of the steps will commence.

•       6.63  The foundations to the steps will be constructed in and around the existing Pedway structure in advance of its demolition. Therefore, there will be a need to utilise small/specialist plant, such as restricted access piling rigs that will be able to access the low headroom areas beneath the existing Pedway to construct the piles.

•       6.64  Phase 2 - This phase will commence within an agreed window of time to minimise the impact to WNSL. The first stage of demolition will focus on removing the Pedway structure from the area of the new staircase construction. Once this is removed, the demolition will focus on removing the remainder of the Pedway (as it runs across Engineers Way towards Olympic Way and Wembley Park station north of the Stadium). A road closure of Engineers Way will be required whilst the Pedway is removed across the carriageway area (details as to the number and timeframes required for the road closures are not yet available but will be agreed, at the proper time, with the Council).

•       6.65  The construction of the staircase is anticipated to be a combination of pre-cast and cast in- situ concrete. It is anticipated that the bridge podium section that will connect to the Stadium will be cast in-situ and the staircase will be formed from precast structural elements. The staircase is of a modular construction and will follow a step by step process that will be prescribed by the designer and supplier. Throughout this phase of heavy lifting it may be necessary to have lane closure on Engineers Way to facilitate easy delivery and unloading of the precast elements. Pedestrian management will be a key feature of this phase to maintain safety exclusion zones around the works.

•       6.66  Phase 3 - The fit out of the staircase undercroft will commence as soon as all overhead working is complete and it is safe to do so. The final landscaping will be constructed during the WNSL events season. Ahead of this phase there will be agreed processes and access routes to limit the level of non-working and disrupted time (as has been managed through the delivery of the Olympic Way Zone A works).

•       6.67  The construction of the landscaping and public realm works will be undertaken in two sections that will run concurrently: Olympic Way (from the boundary of the Zone A works) to Engineers Way and the Olympic Steps area comprising land south of Engineers Way to the Stadium.

Back in 2018 Wembley Matters considered how much disruption would be caused by the works LINK

There is more to the Olympic Way improvements that just the steps, although Brent's Infrastructure Delivery Plan for 2020-2014 only refers to the step,s a total of £40m is to to be spent  with a funding gap of £17m ,





There is of course another major project that has been delayed and for which no start or completion date has been confirmed.  That is the reconnection of North End Road to Bridge Road. The plan was regarded as  important to allow buses to avoid the stadium on event days and to make up for the loss of the road that currently runs beneath the pedway. Earlier plans appeared to envisage the removal of the ramp down to Olympic Way from Bridge Road but this illustration appears retains them. The Michaela School would now be on a through road rather than the present pedestrianised section. New high rise buildings are planned for the site presently occupied by the College of North West London and the Wembley Retail Park and temporary theatre on the former TV studio site.


The North End Road connection
 It is not clear from the documentation whether the £40m includes these plans. I wrote on July 1st 2019:
The works to reconnect North End Road, Wembley with Bridge Road (presently connected by steps and a ramp) were due to start today but Brent Council informs Wembley Matters that they have been postponed but are still due to be finished for January 2020.

In May Brent Council announced on its 'Current Wembley Regeneration Projects' page LINK:
The council will soon start work on connecting North End Road to Bridge Road. This will benefit existing residents by providing an alternative route across Wembley Park to access the North Circular Road, improving the traffic flow in the area. This route will not be affected by event day closures, enabling an available vehicular route at all times - particularly useful for residents of North End Road, who are impacted by the road closures on event days, and bus users.

The contractor delivering the works

VolkerLaser is undertaking the works at North End Road on behalf of Brent Council.

A VolkerLaser team will be on site from June 2019 to start the works, and the project is expected to be completed by early 2020. During this time, the team will endeavour to undertake the works with as minimal disruption to local residents and businesses as possible.

VolkerLaser is part of VolkerWessels UK and are one of the UK’s leading multi-functional contractors. They have a proven track record of success within the highway sector, completing some award-winning civil engineering projects across the last 25 years.

The original timetable published on  24.6.19 in the Brent Council 'Works Bulletin' listed works on Bridge Road for reconnection starting on May 20th 2019 and finishing on June 30th 2019, lasting 42 days. Associated works for reconnection at North End Road, including the road closure, were to last for 222 days from May 13th 2019 to 20th December 2019.  Clearly Brent Public Realm Scrutiny Committee will want some explanation for the delay and completion for January 2020 looks a real challenge.
There was some fumbling around on the site  but certainly nothing substantial and no completion in January 2020.

I wonder if the Public Realm Scrutiny Commitee could investigate?



Thursday, 5 March 2020

Wembley Park Station has its own paddling pool - urgent action needed!


Wembley Park Station has long had a problem puddle outside its Bridge Road exit but with the recent heavy rain the puddle has become a pool.  This was the scene during this evening's rush hour as pedestrians on their way to the bus stops tried to negotiate water a couple of inches deep in places.

Things got much worse when the Jubilee line shut down at Neasden due to a points failure. Passengers poured out of the station to use the alternative bus routes and some walked on the road on their way to the bus stops, the other side of the railings, to avoid getting their feet soaked.  I saw one man with a baby in his arms and holding the hand of a toddler  balancing along the pavement on the road side of the railings who could easily have been clipped by buses pulling up to the bus stop.


When I tweeted about this to Brent Council and Transport for London (above) on February 13th Brent Customer Services replied the next day.
Thank you for bringing this to our attention. We will investigate the cause of the pooling of water in this location.
I don't know if an investigation has taken place but urgent action is required before there is an accident.

Monday, 1 July 2019

Works on Bridge Road-North End Road, Wembley, reconnection postponed. Completion still promised for January 2020


The works to reconnect North End Road, Wembley with Bridge Road (presently connected by steps and a ramp) were due to start today but Brent Council informs Wembley Matters that they have been postponed but are still due to be finished for January 2020.

In May Brent Council announced on its 'Current Wembley Regeneration Projects' page LINK:
The council will soon start work on connecting North End Road to Bridge Road. This will benefit existing residents by providing an alternative route across Wembley Park to access the North Circular Road, improving the traffic flow in the area. This route will not be affected by event day closures, enabling an available vehicular route at all times - particularly useful for residents of North End Road, who are impacted by the road closures on event days, and bus users.

The contractor delivering the works

VolkerLaser is undertaking the works at North End Road on behalf of Brent Council. 

A VolkerLaser team will be on site from June 2019 to start the works, and the project is expected to be completed by early 2020. During this time, the team will endeavour to undertake the works with as minimal disruption to local residents and businesses as possible. 

VolkerLaser is part of VolkerWessels UK and are one of the UK’s leading multi-functional contractors. They have a proven track record of success within the highway sector, completing some award-winning civil engineering projects across the last 25 years.

For further details about the project contact Rachel Best:
Email: Transport.Strategy@brent.gov.uk
Call: 0208 937 5600
The original timetable published on  24.6.19 in the Brent Council 'Works Bulletin' listed works on Bridge Road for reconnection starting on May 20th 2019 and finishing on June 30th 2019, lasting 42 days. Associated works for reconnection at North End Road, including the road closure, were to last for 222 days from May 13th 2019 to 20th December 2019.  Clearly Brent Public Realm Scrutiny Committee will want some explanation for the delay and completion for January 2020 looks a real challenge.

Wednesday, 26 June 2019

Works to demolish Wembley Stadium pedway & replace with steps will now not take place until AFTER Euro 2020


Controversial works to replace the Wembley Stadium pedway with steps will not now take place after Euro 2020 despite Brent Planning Committee being told in September 2018 that they would be completed for the Euro 2020 matches to be played at Wembley.

EXTRACT FROM COUNCIL MINUTES LINK
Members heard that the steps were intended to be in place for 2020 when Brent would become the Borough of Culture and Wembley National Stadium would host European Nations League finals.
-->The European Nation Leagues Final final will be held on July 12th 2020. One of the reasons cited for the urgency over pedway replacement was it would would provide a fitting modern gateway to European matches at the stadium as well as contribute to public realm 'improvements' to showcase the Brent Borough of Culture 2020. Now they won't be in place until after both events.

Brent Council told Wembley Matters today that works are scheduled to start in late 2020 and will be completed in Summer 2021.

The works will be complex and disruptive. Unfortunately the Site Management Plan no longer seems to be available on the Brent Council website but I published extracts on Wembley Matters HERE

Controversy was not just a matter of whether the pedway replacement was needed, and whether steps would be safe, but also the fact that Brent Council was using money paid to the Council (almost £18m) by Quintain in Community Infrastructure Levy (CIL) to spend on the pedway replacement, reconnection of North End Road to Bridge Road and other Olympic Way improvements when many felt it could have been spent on infrastructure improvements elsewhere in the borough.

The commencement date for the North End Road-Bridge Road reconnection works has been postponed from the July 1st start date but is still expected to be finished by January 2020.


Saturday, 7 July 2018

£6m plan to re-connect Bridge Road and North End Road in Wembley



The existing steps and ramp that provide pedestrians access to Olympic Way and North End Road from Bridge Road (closed when crowds leave the stadium)

The Brent Cabinet will make a decision on a £6m plus scheme to rejoin North End Road, Wembley Park to Bridge Road at its meeting on July 16th.  An artist's visualisation of the project will not be published until the day of the meeting but I expect the road extension to run close to the Michaela Community School. (see above)

The plans has been on the back burner for many years but has become a necessity as a result of the Council's decision to fund the removal of the Wembley Stadium pedway and its replacement by steps. That scheme plus other public realm improvements  on Olympic Way is costing £17.8m the Council has allocated from the Community Infrastructure Levy (CIL) and the additional £6m is also likely to come from CIL.

The officers' report states:
A planning application has recently been submitted to remove the existing pedway that enables spectators to cross Engineers Way. This will require Engineers Way to be closed prior to events as well as afterwards, The outcome of this is there will be not east-west vehicular movements across the growth area for an extended period of time, further impacting on residents and businesses as well as reducing the number of buses able to access the twin centres and shopping areas (Tesco and IKEA).

If the pedway is replaced by steps the construction of the North End Road connection becomes essential to provide a vehicular route which is not impacted by the vehicular exclusion required on event days around the stadium. Additional benefits could be [my emphasis] buses would also not be required to divert away from the area enabling journeys to be completed without inconvenience. If implemented it is expected that the steps will be constructed in 2019.
I am not sure the residents of North End Road will welcome the transformation of what is currently a quiet road into a busy thoroughfare, perhaps with buses, although some motorists may welcome better access.  I will await confirmation from TfL regarding the practicality running buses on this alternative route.  Certainly residents on my estate, Kings Drive, are frustrated by the curtailment of the 206 bus service on Wembley event days.

In addition to this major infrastructural project the Cabinet will also consider proposals to introduce 'two-way working'  on South Way between VDC Careys and Great Central Way, Fifth Way and Fourth Way 'to improve the operation of the highway network on event days and provide some mitigation on the delay experienced by residents and business in North End Road through avoiding having to flow around the gyratory with event day traffic.' VDC Careys will accommodate the new Wembley Stadium coach park, becoming operational in January 2020.

Officers argue:
Two-way working is also proven to lower traffic speeds just through the experience of having oncoming traffic movements, this will assist in providing a better environment for pedestrians and cyclists to be in and encourage sustainable and active travel into this vehicle domination area.

The outcome is intended to achieve an appealing gateway to Wembley, improved public realm for the existing community and improve the environmental conditions to attract future investment.
Persuaded?