Friday, 11 April 2025

All routes Wembley High Road and Wembley Triangle to re-open Friday April 19th as upgrade completed ahead of schedule

 From Brent Council

Wembley Triangle – 1 month ahead of schedule

We are pleased to inform you that the works are progressing really well and we should be opening all routes on Friday, 18 April 2025.

Please find below summary timeline for the remaining works:

  • Saturday, 12 April. Wembley High Road will open on temporary road surface from 5am. Access to Wembley High Road from Wembley Hill Road and Ecclestone Place will remain closed.
  • Monday, 14 April. Wembley High Road will be closed for road resurfacing from 8pm to 5am. Access to Wembley High Road from Wembley Hill Road and Ecclestone Place will remain closed.
  • Friday, 18 April. All routes will be open as usual as our upgrades will be complete.