Thursday, 11 November 2021

EXCLUSIVE UPDATED WITH COMMENTS: Wembley Matters publishes the full Ridge Report into the defects at Granville New Homes built by Higgins Partnership that require £18.5m remediation

Brent Council has disclosed the Ridge Report to Wembley Matters following a Freedom of Information Request. It shows just how bad the condition of this 'new build' was. According to the Scrutiny Minutes, this report has never been discussed with Higgins Partners who built Granville New Homes, no redress has been sought, and Higgins is working on at least three contracts in the borough worth millions. 

There have been a small number of redactions for personal/identifiable information. (Click on bottom right corner for full size)

Philip Grant has read the Ridge Report, and has commented:

If I remember correctly, Scrutiny Committee were told that the Ridge Report was commissioned by First Wave Housing, and that Brent Council were not informed about its findings until after FWH had received the Report.

The Ridge Report clearly states that the client was Brent Council AND First Wave Housing. So, on whose instructions was it commissioned, and who paid for it?

The Report says that it was commissioned because Brent Council and FWH were aware of many serious problems at Granville New Homes:-

'Brent Council & First Wave Housing have noted the below issues:

 Water leaks resulting in severe damp and mould within the flats.

 Rotting timber windows due to water leaks and severe condensation.

 Roof capping defects allowing water to penetrate into the cavity behind the cladding.

 Water ponding on the flat roofs.

 Inadequate falls to the communal walkways resulting in water flooding the lift shafts.

 Water tracking into the flats from the service ducts in the communal areas.

 Cladding failure allowing water penetration through the walls.

 Inadequate fall to the balconies allowing water to penetrate the flats through the doors. 

 Difficulty sourcing spare parts for remedial works to the windows.'

Claims that Brent Council were not aware of the serious problems until after the Ridge Report was received in May 2021 appear to be untrue. 

After all, Brent Council's housing staff had been managing the GNH properties on behalf of FWH since 2017!

Cabinet decided to "consult" with the residents about the work which needs to be carried out. Has this been done yet?

People are living in these flats which were poorly designed, with many examples of poor workmanship by the builders who constructed them, both major contributors to the problems which now have to be put right.

The report says that a year should be allowed for the design, procurement and statutory consents needed for the remediation work, which itself is then likely to take around 18 months to carry out. I hope that Brent Council will get on with the job, and make sure it is done properly this time.

 There appear to be some discrepancies between the Ridge Report above, and how it was presented to Cabinet on 11 October 2021, in a report signed off by Brent's Chief Executive.

The opening paragraph of the report to Cabinet members says:

'First Wave Housing (FWH) has commissioned a report from Ridge Consultants
to investigate water penetration, cladding, fire safety and window issues at
FWH’s Granville Road, Princess Road, and Canterbury Road blocks (otherwise
known as Granville New Homes). Ridge have recommended that works be
carried out at the blocks to remediate these issues. It is estimated that the cost of works will be £18.5m. This makes the FWH business plan unviable.'

This clearly states that fire safety was investigated as part of the Ridge Report; but the report itself (see bottom of page 24 of the document in the blog above) says:

'Fire safety matters, relating to the cladding have not been commented on in this report as they are excluded from the scope. From what was seen, during the opening up of the cladding, there are a number of issues which should be further investigated by a façade specialist and fire engineer. These include possible combustible insulation and seemingly a lack of cavity barriers within the cladding system. The cladding systems should be reviewed, from a fire safety perspective, as a matter of urgency.'

Page 26 of the Ridge Report gives the budget cost estimates of the work identified as a result of this consultant's investigations:

'TOTAL COSTS by block:

Granville Road East £2,185,000
Granville Road West £2,475,000
Peel Square £4,550,000
Pilgrims Corner £4,435,000

TOTAL £13,645,000'

Clearly, there is a difference between the £13.645m figure in the Ridge Report which has now been disclosed under FoI (and which was not made available to the members of the Audit or Scrutiny Committees, when they considered the problems and proposed solutions over Granville New Homes), and the £18.5m figure in the report to Cabinet.

Was there a second specialist report on the fire safety issues, with the estimated cost of that remediation making up the almost £5m difference between the two figures?

If not, what is the explanation for that difference?

And if there was a separate fire safety defects report, why was that not mentioned in the report to Cabinet, and why has that report not been disclosed to councillors, or made public?

Wednesday, 10 November 2021

Concern over felling of Malvern Road plane trees

 

Residents have raised concerns over the proposed felling of pollarded mature trees in Malvern Road, Kilburn. They appeared to be healthy and it was reported that all would be felled.

Brent Trees officer , Gary Rimmer said, 'We are removing 2 plane trees from Malvern Road because they have decay at their base, the removals are the result of our own surveying, no residents have asked for them to be removed.'

Local tree expert  Suzanne Morpurgo (Forestry Commission/RHS) told Wembley Matters that the Council removes the trees to stop bracket fungus spreading. Early action is taken to ensure that a falling tree (plane trees are tall and heavy) does not cause danger to the public. Higher winds, higher rainfall at different times, then droughts and heatwaves - all stress the trees to a far greater level than pre climate change acceleration

As we approach the season of dormancy and therefore tree works, people in Brent will be on the look out for any unnecessary loss of trees.



Granville New Homes, Merle Court, Bourne Place - an account of South Kilburn's new build disasters. Who will take responsibility?

 

A section of Higgins Partnership's Granville New Homes

I returned to South Kilburn last week in order to update Wembley Matters on the progress of this massive development.

Granville New Homes are not called that by its residents, who just use their addresses, but the occupants  have found themselves in a very fraught situation. Brent Council have so far offered no option for residents  be decanted elsewhere when the £18.5m remediation works start.  Even if they wanted to be decanted  it is unclear whether any spare capacity is available.

There is the possiblity that a much needed Tenants and Residents Association will be formed to represent their interests and one of its main tasks should be to ask Brent Council to finance independent legal advice for them.

Ironically, Higgins Partnership who built the defective homes, were chosen by Catalyst Housing to remediate defects in Merle Court (built as a 2012 partnership between Wilmott Dixon, Catalyst  and Brent Council) just around the corner.  Problems were so bad that Catalyst tenants were told that they would be rehoused. LINK I am currently seeking clarification from Catalyst whether this in fact happened. It certainly doesn't look fit to live in at present.

 

Scaffolding around Merle Court

 

Not far away Higgins pop up again at the Chippenham Gardens development (where potential flooding has been highlighted by David Walton HERE)

 

Higgins' Chippenham Gardens build

 

Lastly as far as Higgins goes (well probably not!)  but on the other side of the borough, Brent Council chose them for a £22m contract to build homes and a retail unit on the Hillside/Milton Avenue site in Stonebridge. This is Brent Council and Higgins celebrating the start of the project just under a year ago.

 


It is no wonder that Cllr Southwood, rather anxiously,  sought assurances at this week's Brent Cabinet meeting on the quality of build at the Alperton Bus Garage development where the Council are purchasing the leasehold on 155 housing units.

On to another housing association, L&Q Homes, where their Bourne Place has been a disaster area, highlighted often by campaigners on social media. This 2013 build was a partnership between L&Q and Brent Council and is beset with cladding and heating problems. When the defects emerged Brent Council and L&Q clashed over who was responsible ,with the leaseholders caught in the middle. LINK


The PR plug in the Evening Standard refers to a 'once notorious estate' - it is now becoming notorious for housing scandals!

The contrast between what I found on the ground and the image above could not be more stark:

Bourne Place - temporary heating pipes snake across the ground and above the ground

Temporary heating centre


A resident of Bourne Place told me:

Our entire system failed due to  both plant room issues and burst pipes underground. So L&Q had to hire the temporary heating centre placed in the garden and build temporary pipes into buildings. It has been like this since February. The first stage was to fix the plant room, our own boilers and pump. I believe this is now completed. The  temporary centre will be removed and pipes will need to be adjusted to lead from our plant room into the buildings. The last stage will be to dig out the grounds and replace all underground pipes to connect all 3 buildings again to the repaired plant room via underground pipes. Then these temporary pipes will be removed. It's still long way from completion due to all sorts of delays, some to do with customs and delivery issues from Europe.

 

South Kilburn residents have had to resign themselves to several decades of building works but rely on the 'Considerate Builders' to actually mean what they say.

The building of the HS2 vent next to flats and a primary school was opposed by residents but went ahead with the support of Brent Council who want to build on the initial site next to Queens Park station. A resident told me about being awoken by HS2 works  at 4am in the morning and noise at other unsocial hours.

More disruption is promised by HS2's rather belated investigation of the drainage system at the site - perhaps recognition of potential flood dangers. The HS2 track will run beneath the South Kilburn estate...

 

HS2 Works Entrance

 

Vent works

It is perhaps not surprising that some residents are now looking with an element of nostalgia at the blocks waiting to be demolished. 


The South Kilburn Skyline



Scrutiny Committee minutes lay bare South Kilburn's Granville New Homes scandal

 

Granville New Homes

The Minutes of the special meeting of the Community and Wellbeing Scrutiny Committee of October 7th that examined the scandal of the Granville New Homes, built by Higgins, that will cost more in remediation (£18.5m) than the purchase price.

 

It was a very thorough examination of the issues involved and members’ concern that Higgins was not spoken to about the defects. no redress sought and that this poor build was not taken account of in awarding them current contracts in South Kilburn and Stonebridge, was very clear.

 

The Committee agreed a comprehensive list of recommendations including that they and the audit committee should receive copies of the independent Ridge Report on the defects. Observers were astonished that such a key report had not been presented to the Committees. Two weeks after the meeting in a twitter reply to Wembley Matters, Brent Council said that that a response to Scrutiny Committee's recommendations was being compiled. For the sake of transparency this should be put in the public domain and include the Ridge Report before Scrutiny's next meeting on Monday.


The Minutes 

 

Councillor Southwood (Lead Member for Housing and Welfare Reform) introduced the item which provided the Community and Wellbeing Scrutiny Committee with an update on the options analysis that First Wave Housing (FWH) carried out with the Company’s Guarantor, Brent Council, on finding a viable option to fund and deliver the required remediation works at Granville New Homes. She advised that this was about putting things right, and fixing a historic issue that was not of the making of anyone attending the meeting that evening but which needed to be responded to in the present, looking to the future. 

 

The proposal related to Granville New Homes which were built in 2009. The Committee heard that, following the Grenfell tragedy, all Council blocks were inspected to check cladding materials and also for wider fire safety issues. Granville New Homes was found to potentially have cladding that was not fire safe, therefore FWH went through the process of getting relevant inspections into the fire safety of the blocks. A Waking Watch had been in place in the blocks since October 2020 as a result of the concerns raised through those inspections. 

 

After further intrusive works were conducted, the total cost estimate needed to remediate the properties was substantial at £18.5m, which had considerable financial implications. Councillor Southwood advised that the proposal to Cabinet was to transfer 85 (84 social tenants and 1 leaseholder) Granville New
Homes properties from FWH into the HRA, and further to transfer 25 intermediate rented homes into i4B stock. This recommendation was the option that met all the priorities set out in the Cabinet report.

The Chair thanked Councillor Southwood for her introduction and invited the Committee to raise comments and questions, with the following issues raised:

Further context on the history of Granville New Homes was sought, including when the Board and Guarantor became aware of the defects. Peter Gadsdon (Director of FWH) advised that FWH took over the stock from Brent Housing Partnership (BHP) in 2017. He advised that effectively BHP had stock that was unable to go into the HRA at the time which included Granville New Homes, which FWH took on. He advised that the first time the Board and Guarantor were aware of the full extent of the issues to the stock was in May 2021 when the Ridge report was received. He advised the Committee that the Audit Committee had also been sighted on the issues in the blocks, including the extent of the financial implications, although they had not seen the Ridge report. This was part of the Audit Committee’s Forward Plan who, on an annual basis, looked at the business plan for FWH as a subsidiary to the Council. The issue had also been discussed with FWH’s external auditors.

The Committee requested further details about how the report was commissioned and who had oversight of the defects, and wanted further details on the considerations given to legal due diligence and financial due diligence. Peter Gadsdon advised that as a result of the government MHCLG asking for all properties over 18 metres with any form of cladding to be reviewed, the Board took the decision to review the Granville blocks at 17.5 metres, where the fire service reviewed the fire safety arrangements and were the first to alert the Board in October of 2020 of issues with the fire safety arrangements. The Waking Watch had been implemented since October 2020 as a result of the advice received to ensure the safety of residents in the event of a fire. Further intrusive works were commissioned following this as there was a need to cut into walls, take windows out and break through walls to understand what the composition was, which Ridge conducted, including in a number of flats which were empty. Following the fully intrusive works where Ridge could see the full extent of the issues, the Board received the final Ridge report in May 2021 and made the Guarantor aware. In response to what financial due diligence took place, Minesh Patel (Director of Finance, Brent Council), representing the Guarantor, advised that Ridge were appointed as independent specialists to work through the surveys and provide an estimate, which internal Finance Officers and Officers on behalf of FWH had checked to ensure was correct. He advised that it was an estimate and they would not know the true cost until the work had been started. Hakeem Osinaike added that Ridge had been commissioned to undertake the intrusive works with a good quality specification and therefore he had confidence in the report submitted by Ridge.

The Committee queried whether the Council, as Guarantor of FWH, had chosen to challenge FWH on the issues. Minesh Patel advised that the Council’s role as a Guarantor was to meet with the Board of FWH on a regular basis to go through Key Performance Indicators and understand how the Company was running. The Guarantor had not been made aware of any issues prior to the final Ridge report.


Hakeem Osinaike (Operational Director Housing, Brent Council) advised that the properties were managed by Brent Housing Management (BHM) on behalf of FWH, and they had managed the repairs in those blocks up until the inspection. He advised that it was in rectifying the fire safety issues a decision was taken to rectify any other issues as well.

The Committee noted that Higgins had been appointed to design and build the blocks in 2009, and had heard from residents and staff that there had been problems with the blocks since they were built. They queried what legal action against Higgins, as the contractor, had been pursued, considering the roofs had been previously replaced when FWH took over the building. Peter Gadsdon confirmed that BHP had replaced one of the roofs before FWH took over, and once FWH had taken over they had done works on water ingress issues and had planned to replace all roofs over time as part of previously published business plans for the Company, with an original cost estimate of £2m – 2.5m. With regard to any legal action taken, Peter Gadsdon advised that the records showed the building had been signed off and handed to the Council, but he was unable to comment on anything before 2017 when FWH took over the buildings. He advised that FWH had not had any conversations with Higgins regarding the defects which they were made aware of in May 2021. Legal advice was previously sought about whether there was any chance of redress but due to the passage of time were advised it was unlikely. The Board’s priority was to ensure the properties were repaired back to safety.

Continuing to discuss the contract with Higgins, the Board queried why the Council were not communicating with them on this considering they were current contractors on other blocks being built. They queried whether there was a risk of this happening in other blocks that had been built or were being built. Minesh Patel advised that he did not have the details on the construction contracts with Higgins as that was a procurement process, but nothing had been brought to his attention that there were any concerns on any of the blocks Higgins had worked on.


Councillor Southwood advised that the contractor had been awarded work by the Council through a procurement process without prejudice, the specification of which would have applied modern building control and expectations to whatever they built, and which would include monitoring on the delivery of their contracts. From a FWH perspective it was highly unlikely any other stock would have these issues as Granville New Homes were the only medium rise buildings in the assets. Peter Gadsdon added that, like the Council, FWH and i4B commissioned stock condition surveys and had Fire Risk Assessments in place and there were no issues in that regard. Councillor Southwood agreed to provide written assurances to the Committee that there was no issues in any of the blocks Higgins had worked on, and further information on the procurement process such as whether past performance of a contractor was considered before awarding a contract.


The Committee considered the financial implications of the proposals, and Ravinder Jassar (Deputy Director of Finance, Brent Council) confirmed that no funds were being written off to the Council’s general fund. FWH would refinance the debt but still have a debt to the Council and service that debt over a 50 year period. The remaining stock in FWH remained with positive cashflow that allowed the servicing of that debt.

 

The Committee queried what risk assessments had been done considering the rise of inflation and high likelihood of a rise in interest rates. Councillor Southwood advised that was why the paper was being brought to Cabinet, as every penny borrowed against the HRA was needed and the Council wanted to minimise the amount per year that tenant’s rent was used to pay interest towards. It was in the Council’s interest to secure the borrowing as soon as possible before interest rates changed. Further considering financial implications, the Committee highlighted the labour shortages, and increased labour and material costs as a result of the pandemic, and queried whether that had been budgeted for in the contingency. 

 

Peter Gadsdon advised that the costings were estimated in May of the current year, post pandemic, with those things taken into consideration as much as possible. In considering the finances of FWH, Committee members highlighted that FWH’s most recently published accounts showed a discrepancy in the valuation of the Company, and asked about the justification and reasoning behind the valuation. Finance Officers agreed to provide a written explanation to the Committee. In terms of the financial implications to i4B, Ravinder Jassar advised that i4B would acquire the units for £3.5m, with an average weekly rent of £324 per unit per week, which made the purchase price per unit around £140,000. This was within the overall affordability limits of i4B and was a reasonable deal for them.

The Committee queried the rationale behind the proposal and why the Council were not able to lend FWH money to undertake the remediation. Ravinder Jassar explained that FWH were not able to afford the remediation works required even if they tried to refinance at a lower rate, and the business plan would no longer be viable. The option to demolish and rebuild had also been considered but was not financially viable. The Committee were advised that borrowing with the HRA was cheaper than lending to FWH, and the Council could not lend money to its subsidiary at the rate it could get as a Local Authority.

The Committee queried whether there was a risk to the business plan of a loss in rental income should a large number of tenants exercise the right to buy once they were brought in to a secure Council tenancy. Hakeem Osinaike advised that the right to buy in itself did not affect the financing of the transfer, and the income from any right to buy would be used to build New Council Homes. Councillor Southwood gave assurance to the Committee that the Council knew how many people exercised the right to buy on average per year, and she had received assurance from officers that there was no reason to think the proportion would be greater amongst this cohort. The financial assumptions were modelled on the same as any right to buy across the HRA, and if a greater proportion exercised that right there was contingency built in to the revenue forecasting. Peter Gadsdon added that 72 of the 84 social tenants had right to buy when the blocks originally transferred into BHP with only 1 tenant exercising that right. The Committee highlighted that the refurbishment of the blocks may change the numbers exercising their right to buy.

In considering the tenants within the block, the Committee queried what the proposals would mean for them. Councillor Southwood advised that for the 85 residents transferring to the HRA, the tenants would become full secure social tenants with the same rights as anyone else in the HRA, which she highlighted was one of the most secure forms of housing. The one leaseholder would become a Council leaseholder. The intention was for the Council to waive the charging of the cost of refurbishment to the leaseholder. The rents for the 84 social tenants would not change, and neither would the 25 intermediate rented properties proposed to transfer to i4B. In addition, there would be no change in their housing management services, which would continue to be delivered by Brent Housing Management (BHM). The Ridge report predicted that the works could be carried out without decanting residents.

With regard to whether tenants would get a rent waiver, reduction, or rent free period, the Committee were advised that none of those issues had been considered yet but would be as part of the consultation process. Hakeem Osinaike advised that it was not usual for the Council to offer rent reductions when carrying out major refurbishment.

The Committee asked how tenants would be engaged and how resident engagement had gone so far. BHM undertook engagement on behalf of FWH. At the time of the fire survey all residents were written to with an explanation of the issues, the Waking Watch and the work that was done to strip out flammable portioning. An online Zoom meeting had also been set up for tenants to raise concerns, however only a few people had joined. The Committee were advised that up to the point of the Committee meeting there had not been much response from residents. As such, BHM were engaging with residents individually when repairs were carried out in their homes, and everyone was aware of the issues and the way they were being taken forward. Further communications to residents would be necessary with the next steps.

The Committee queried whether the Council had considered carrying out energy efficiency and decarbonisation works in tandem with the remediation. Councillor Southwood advised that any discussion about decarbonisation works for those homes would be considered in the context of them being part of the HRA. The £18.5m in costs referred only to structural and safety works required and not any additional cosmetic work such as updating kitchens or bathrooms or decarbonisation works. She advised that the cyclical maintenance schedule would mean the properties under discussion would be due for new kitchens and
bathrooms around the time of the works being undertaken, so while builders were in and tenants were disrupted it made sense to do as much work as possible. Hakeem Osinaike added that as the internal and external walls had been stripped back as part of the intrusive surveys, when they were reconstructed they would meet the required energy efficiency targets. In terms of the Council’s decarbonisation work they were currently looking to retrofit a street property. No decarbonisation grants had been considered for the Granville New Homes properties.

The Committee questioned the delegated authority for the decision and Councillor Southwood advised that the issues crossed portfolios, but because the issue was specifically a technical financial recommendation it sat with the Deputy Leader, Councillor McLennan. Councillor Southwood was presenting to the Scrutiny Committee as they had asked to look specifically at the HRA, which was within her remit as the Cabinet Lead for Housing and Welfare Reform.

The Chair thanked officers for their responses. In considering their recommendations, the Committee discussed concerns over the reputational risk to the Council, the relationship between the Council and its subsidiaries, the engagement and communication between the residents and the Council and its subsidiaries, the concerns over the building handover process of the blocks, and concerns regarding the commissioning process and contract monitoring of these types of contracts.

The Chair reopened the meeting to provide the recommendations agreed. The Committee RESOLVED:

 

i) To recommend that officers provide assurance that the Council has undertaken due diligence reviews of its subsidiary bodies, including governance, fitness for purpose, financial soundness and reputational risk.

ii) That officers ensure that the Ridge report is made available to the Community and Wellbeing Scrutiny Committee and audit committee.

iii) To recommend that officers review arrangements for entering contracts of this kind, in particular to ensure adequate arrangements are made to ensure appropriate design and build quality, and that the Council has appropriate recourse where latent defects are later identified.

iv) To recommend that officers ensure all potential contractors are made aware of the standards expected by the Council and to ensure these are met before buildings are formally accepted by the Council.

v) To recommend that the Council provide written assurance that it has taken, or will undertake, independent legal and financial advice (including tax) regarding the proposals and next steps.

vi) To recommend that all contracts procured by the Council and its subsidiaries include a review of past delivery of any potential contractors.

vii) To recommend that the Council ensures that where issues are evident in a particular project, all remaining projects by the same contractor are reviewed as a matter of urgency.

 

viii)To recommend that officers review the steps that make up the procurement, commissioning and contract monitoring system to identify any gaps, especially in relation to risk and review. Where risks are identified to recommend that immediate action is taken.

ix) To recommend that the Council puts in place arrangements to ensure learning about this case and any others raising issues of similar significance is shared across the Council as well as with existing and potential future partners/contractors.

x) To recommend that officers establish and publish a comprehensive plan for ongoing engagement with residents.

 

Tuesday, 9 November 2021

Cllr Kelcher's update on situation around City Mission Church's threatened eviction

 

City Mission Church

 Cllr Matt Kelcher (Kensal Green) has circulated concerned residents with the results of his research into the threatened eviction by developer Fruition of the City Mission Pentecostal Church from its Harlesden site:

The Mission Pentecostal Church operates a faith and community facility from the existing building, including a local nursery and foodbank. As a representative of the local community I have visited the site on a few occasions and met people who use the facilities. I know it does great work for the wider community and has a lot of local support.

 

Unfortunately, occupies the building on a “Tenancy At Will’ arrangement, and so has very limited security. On Friday 29 October, Fruition Properties, who are the owners and developers of the site, issued a termination notice effective of Friday 5 November.

 

Until June this year, the building had planning consent to redevelop the site for residential development, granted by OPDC in 2018. The planning approval included a condition that Fruition must secure replacement space for the Mission Pentecostal Church and associated foodbank and nursery as part of the new development.

 

I remember visiting the premises when this application was under consideration (this was as a ward councillor a few years before I joined the OPDC planning committee myself) and the presentation I heard really put the provision of these facilities at the heart of why it should receive community support. I believe it would be unjust for the owners of the site to go back on these promises.

 

This consent lapsed in June 2021 and Fruition are looking to submit a new application. The OPDC have clear planning policy that will require re-provision for the church and any associated community service in any new application. I met (virtually) with the Chair of the OPDC Planning Committee, the Director of Planning and Cllr Harcourt from Hammersmith and Fulham around this time and emphasised the value to church gives to the community. I was pleased that following this OPDC planning officers met with both the developer and church to highlight these requirements.

 

Therefore, whilst we should all join together to campaign to save the church, we should be clear that the OPDC have not been complicit or encouraging of the eviction notice. Indeed, if a new application were to come in for the development of the site, the OPDC have made it clear that they would strengthen the protection that the church/nursery has above and beyond what it has now.

 

Similarly, as the site is in the devolved OPDC area, there is little that the team in Brent can do to block this eviction either. Though I have been in touch with the Head of Planning to discuss the matter.

 

It seems the owners have given up on completely re-developing the site and are trying to eek as much out of the current space as possible by evicting the church. Or, they hope that if they go some time without a church in place, and then re-apply for permission then no conditions will be added to planning consent.

 

It is our job as community representatives to ensure they cannot get away with this by reminding everyone how important these facilities are to people who live in Kensal Green, and that any future for the site must involve the Mission Pentecostal Church.

 

Most recently, I have liaised with Andy Slaughter MP (the building straddles the boundary between Brent and Hammersmith & Fulham so a lot of people are interested in the subject) and will ensure Brent is represented at a meeting he is organising with the developers, if I am unable to attend myself.