Tuesday 7 June 2022

The London Flood Review’s Stage 3 findings re the Kilburn and Maida Vale Area

 Guest post by David Walton

This review https://londonfloodreview.co.uk/ published in May 2022 states that:

 

"New sewer systems are typically designed such that all flows are contained within the sewer (no flooding at ground level) up to a 1-in 30 year return period. Older sewer systems do not have the same requirements and often have a capacity much less than the current 1-in-30 year standard. While the Victorian sewer system for London had ample capacity at the time of its construction, the evolution of the cityscape has had an effect on the ability of the sewer system to cope with the current flows which drain to it. This results in areas of London with sewers which cannot cope with a 1-in-5 year event, despite Thames Water’s continuous upgrade in the sewer network where performance issues are identified".

 

See London Flooding Review Maida Vale Study Area. Its red line includes the South Kilburn Growth Area Tall Building Zone.

 

"We confirm that the scale of the events experienced in July far exceeds any design standards for sewer systems and acknowledge it may not be economical or practicable to implement schemes to eliminate risk for a similar event. Whilst we report specifically on the performance of Thames Water’s assets, due to the scale of the events in July 2021, and the flooding mechanisms, multiple organisations had a duty of care and responsibility to their customers, so the responsibility does not lie wholly with Thames Water."

 

"Typically, Thames Water uses a 1-in-30 year return period design standard for new flood protection schemes; with a range of duration storm events….it is recommended to apply climate change factors to design rainfall, increasing the intensity of the rainfall event."

 

The question, is can South Kilburn Growth Area Tall Building Zone re-development ongoing for 21 years thus far, in legal terms be classified as 'new'? Maida Vale Flooding Review Study Area includes South Kilburn Growth Area Tall Building Zone a  low bowl with hills around in the  stage 3 report.

 

"Analysis of the current network identifies that some drainage systems can be predicted to flood in less than a 1-in-5 year return period rainfall, with properties being affected by frequent flooding. This is true of all major cities in the UK and is not specific to London."

 

"Maida Vale is situated in a low spot, and has the Ranelagh trunk sewer (River Westbourne), Mid Level No. 2 sewer and the North Western Storm Relief sewer running through it. When the Ranelagh sewer is surcharged, flows can back up into connected basements."

 

"Cambridge Gardens (Brent) consists of a new Flooding Local Improvement Project (installation of package pumping stations for individual properties with non-return valves) to isolate individual properties from the sewer network."

 

5 homes in South Kilburn fitted so far by Thames Water.

 

"The Maida Vale Study Area was defined using LiDAR (Light Detection and Ranging topographic) data to identify the topographic area where surface flows could contribute to the tank, which is located in a low spot. The extent of the (low spot) study area can be seen in Figure 5.5."

.

Page 55 of the London Flooding Review pictures Chippenham Gardens, Brent, that in July 2021 become a sewage lake.

 

"We confirm that the scale of the events experienced in July (2021) far exceeds any current design standards for sewer systems and it may not be economical or practicable to implement schemes to eliminate risk for a similar event. We will also look at more holistic recommendations, such as ways of Thames Water responding to similar incidents in the future, increased monitoring and warning systems, engagement with customers, and how TW, and possibly the wider industry, could consider setting out their modelling approach and design criteria for flood alleviation schemes in the future. Due to the scale of the events in July 2021, multiple organisations had a duty of care and responsibility to their customers, so the responsibility does not lie wholly with Thames Water. We will look at how data and communications are shared across organisations, what community groups and individuals can do to improve their own resilience and how planning policy can be changed to reduce flood risk and the impact of flooding."

 

Brent the  Lead Local Flood Authority should protect and invest in what remains of South Kilburns public owned modern natural parks and bowls flood defence system built in the 1960's and 70's.

 

David Walton

FLASK (Flood Local Action South Kilburn)

 

Monday 4 April 2022

Call for heat network protection as government’s backstop fails to protect these customers - price rises of up to 700% reported

Wembley Matters has publicised the difficulties ahead for residents whose new blocks are linked to a District Heating Network. These include blocks in South Kilburn and Wembley.  Because there is a single heating source for all the flats in the block  the gas is counted as commercial rather than domestic and thus the cap on bills is not applicable. In addition residents do not have the option of changing their heating supplier as that can only be done by the managers of the block.

Huge bills are anticipated giving rise to great anxiety, particularly those residents of South Kilburn who are being moved from Brent Council properties with their own domestic heating to housing association blocks on District Heating Networks.

There has been next to no information on how this will affect residents although one pensioner anticipates that heating bills alone will be more than his total income.

The Heat Trust issued this statement on Friday:

As approximately 22 million customers brace themselves for Ofgem's price cap rise today, more than half a million households on communal and district heating networks remain locked out of any protection – leaving them exposed to even bigger, unrestricted price rises.

Consumer protection body Heat Trust is warning that urgent government action is needed to support those living on heating systems that are not protected by the price cap.

Heat Trust, the independent national consumer protection scheme for heat networks, says those living on communal or district heating systems are set to be amongst the worst affected by the soaring cost of gas – with residents facing the prospect of being unable to afford to heat their homes.

The government’s price cap does not currently apply to the heat network market, where operators buy gas on the commercial rather than the regulated domestic gas market.

The Director of Heat Trust, Stephen Knight, has written to Kwasi Kwarteng, Secretary of State at BEIS, to request that 500,000 households are not overlooked as the government looks to ease the financial pressure on families and has been promised a meeting with the Secretary of State, alongside others from the sector, later this month.

Heat networks are seen as a major part of the UK’s decarbonisation plans, and can deliver low-carbon, low-cost energy to homes. However, as the market is currently unregulated, consumers are not protected in the same ways as other energy markets. 

The wholesale gas price, which until last autumn had averaged around 1.5p/kWh for decades, peaked at 27p/kWh at the start of March and has averaged around 10p/kWh in recent weeks. This means that when heating operators renew their commercial gas contracts, they are seeing massive increases, which are often passed straight on to consumers.

Consumers and landlords operating heat networks are already reporting examples of price rises of up to 700% - the equivalent of the price of a pint of milk rising from 60p to £4.80.

Heat Trust is calling for government intervention to include:

  • Ensuring heat network operators and their consumers receive government support to ensure that their bills rise no faster than those of domestic gas customers.
  • Bringing forward its plans to regulate the heat network market via Ofgem which were confirmed in December last year,
  • Bringing forward plans to help heat networks improve their efficiency to reduce heat wastage.

Stephen Knight, Director of Heat Trust, said:

The government is committed to making heat networks a key part of its energy policy, and must not leave families living on these schemes behind.

Heat networks have the potential to offer low-cost, low-carbon heat, but without intervention, hundreds of thousands of families are facing horrendous and unaffordable heating bills.

Heat network operators are keenly awaiting further news of the government’s Heat Network Efficiency Scheme (HNES) aimed at improving the performance of communal heating projects.

The HNES Demonstrator £4.175m grant scheme has already supported a number of communal networks to improve their performance, but the full scheme is not currently due to be launched for another 12-months (spring 2023), and Heat Trust wants to see this scheme brought forward and expanded to cut bills by reducing heat wastage.

Heat Trust is also calling for changes to the Landlord and Tenant Act rules which currently make it difficult for landlords to buy gas more than 12 months in advance, making them vulnerable to price fluctuations. If they could buy gas for longer periods of time, it might protect consumers from market volatility.

Knight added:  

Our mission is to protect heat network customers.

Commercial gas price increases of this magnitude are simply not sustainable for heat network customers. They are driving up household bills in unprecedented ways – many people will have to choose between heat and food.

Heat networks are commonly used in blocks of flats and are becoming increasingly common with social landlords, meaning the most vulnerable people in society are the ones most affected by the current crisis. We can’t let that happen.


Tuesday 29 March 2022

UPDATED: South Kilburn: Flagship or neglect?

Guest post by Pete Firmin, chair, Alpha, Gorefield and Canterbury Tenants’ and Residents’ Association.

 

Brent Council – with the support of planners and architects - likes to praise its regeneration of South Kilburn as a model for others.

 

Yet, beyond the issue of the dubious quality of some of the new housing built in the area, raised in Wembley Matters many times, there is also a big issue around general neglect of the area.

 

To be clear, the area described here, a small part of South Kilburn, is not due for `regeneration’ anytime soon. It does not figure in any masterplan. Not that, even if it was, this would excuse the level of neglect shown here.

 

Everything here has been reported to Brent Council, individual officers and Councillors dating back to November of last year if not earlier.

 

To start at the steps at the corner of Coventry Close and Kilburn High Road. These broken steps have been reported with no response received.

 


 

This rubbish dump has been growing steadily for the best part of a year and reported many times on the Cleaner Brent App. It just gets closed quickly with no explanation. It is not directly on Brent land but is clearly a health hazard.

 


 

This patch of ground (known to residents as the Bermuda Triangle) was created when regeneration hit the area 7 years ago. They still haven’t sorted out whether Brent or Catalyst is responsible for its upkeep, so it just accumulates rubbish.

 


 

Clearly Brent’s responsibility, overflowing like many bins along Cathedral Walk footpath.

 


Mattresses abound, this one was photographed by an estate officer two weeks ago. It is propped up by the metal frame for previous recycling bins. We were promised when they were replaced (a year ago) that they would be removed.

 


 

Broken pane of glass in door of Gorefield House, reported last November.

 


The wonderful bin store next to Gorefield House. Erected by Catalyst during regeneration. For their residents they put up a brick  bin store, but Brent tenants only get a wooden one, which has been falling apart since it was put up. Too near the flats, overflowing bins, never fully cleared. We’ve been told someone in an office worked out how many bins are needed for the number of households…..

 



 

5 of these 7 lights along a footpath created in regeneration have been out for more than 5 months. We’ve been told the issue has been escalated…..

 


 

Damage caused by the flash flood last July. Brent had to be pestered to do anything at all, but we have been left with this botched job which is causing accidents. 

 


 

I could go on, like the numerous street lights not working (one of which has never been connected to the mains), the lift out of order for over a year, and much else, but I hope you get the picture one of a Council which doesn’t seem to care.

 

Pete Firmin

 

EDITOR'S NOTE: Pete's problems in getting responses is well illustrated by this exchange that took place only yesterday.



 

 

 


Tuesday 22 March 2022

South Kilburn residents will have to endure a summer of 24 hours a day, 5 days a week, work on the HS2 vent. Is Brent Council concerned for their health and wellbeing?

 


Seven years ago South Kilburn residents demonstrated against the siting of an HS2 vent on the estate because of the disruption its building would cause and the fact that it was right next to a primary school.

They were even more furious when they discovered that their own council, Brent Council, had lobbied to have the vent moved to the estate, already suffering from disruptive regeneration, from the original site on council owned land next to Queens Park station.

Years of noise, dust and stress have followed so residents were even more distressed to have a warning from HS2  LINK of worse to come.  South Kilburn resident Pete Firmin told Wembley Matters:

HS2 seems to be able to work whenever it likes, doing whatever it wants, with the blessing of Brent Council. The Council itself never communicates with local residents about the works, and as far as anyone can tell, doesn't monitor whether HS2 keeps to even the few restrictions on its working hours etc. Neighbours of the vent shaft have given up complaining, because nothing happens. How inadequate protection from noise and dust really is may be indicated by the fact that HS2 lists further work on the retaining wall they already erected between the site and Carlton House as one of its next jobs. 

 

Since persuading HS2 that the vent shaft should be in the middle of the estate rather than on the empty Queens Park station car park, Brent, for all intents and purposes, has washed its hands of any responsibility. And HS2 is no longer willing to meet residents together, insisting all "consultation" is one to one.


No recognition by either Brent or HS2 of the stress and exposure to noise and dust caused by living in the South Kilburn building site for 20+ years

This is part of the communication from HS2 to residents:

Extended working hours within the Canterbury Works site

 
We wrote to you previously regarding extended hours while we build the ventilation shaft. The sprayed concrete lining (SCL) works were due to start on the 7 March 2022 and continue until September 2022.due to ongoing reviews of our working methods, these works work will now start in late March or early April and will continue until September 2022. The exact date remains subject to confirmation.

The SCL and shaft excavation works will take place throughout the day and night. This must be carried out as a continuous process to avoid collapses and ensure the safety of the workforce within the ventilation shaft during construction. This means that from late March / early April we will be permitted to carry out works 24 hours a day, 5 days a week. We will only carry out works agreed with Brent Council and will adhere to the agreed working hours, noise and vibration limits.

The diagram below shows a cut section of the shaft and how it will be constructed.

Enhancement works within the Network Rail Yard

 
Works are ongoing within the site, near the Network Rail tracks, to prepare for installation of a new site access point via Albert Road. These works will involve the construction of a new access ramp for vehicles to enter the site. As part of these works, we will be carrying out works to strengthen the retaining wall between our site and back gardens at Carlton House. These works are currently planned from May to July but remain subject to confirmation. The works will be agreed with Brent Council and we will write to Carlton House resident with more information.


Whilst we continue the works to prepare for the new ramp and vehicle access point, we will continue using the site access on Canterbury Road for vehicle entry and exit from site.

What to expect during our works

 
During the works outlined in this update you may notice the following within the site:
• Heavy good vehicles – entering and exiting site
• Excavators / excavating activities
• Cranes / lifting operations
• Lighting towers
• Concreting equipment
• Temporary traffic management and signage during work on the public highway

 

 

Monday 21 March 2022

Densification along with misleading figures on community space and green space provide ammunition for South Kilburn residents to fight for a better deal

 

As tables were being cleared after the usual community meal at the Granville Centre in South Kilburn, Leslie Barson  of Granville Kitcheh stepped forward to introduce the evening's rather special speaker.

 She said, 'I have been thinking - you can't have a project without a place to do it. And you need a project for the place.'

The Granville and Carlton Centres have done so much, so many projects, over the Coviud crisis and proved its essential role in the community along with Rumi's Cave (now relocated in Harlesden) and had kept people together: 'We now understand its relevance.'

The planning application approved at the beginning of 2020 is to be actioned over the next few months.

Dr Pablo Sendra from UCL who had led the research project 'Co-designing social infrastructure for resilient communities in post-Covid cities' addressed the crowded room full of local residents. A rare collaborative effort between community and academics.

In his talk Pablo made a number of key points:

Researchers estimated that the Granville Centre over 65 weeks had provided £344,760 worth of volunteer labour,

Quoting the Mayor of London that organisations, projects and buildings need to be more connected and relevant he asked, 'How can the community be more involved in how the building and its spaces work?'

As a result of regeneration South Kilburn had increased in density and needed more community spaces. The 'Community Hubs' hailed by the Council were places to ask the Council for support, rather than for organising activity. Bland spaces were being provided that people did not feel comfortable in. [Later I mentioned the 1970s 510 community centre in the Harrow Road with its old settees and arm chairs, kettle in the corner, that people treated as home from home and housing many organisations involved in anti-racism, immigration, education and campaigns against SuS.]

The former hall in the Granville where people used to meet has been converted into an 'enterprise space' . Overall the research showed that the Council estimate of a overall loss of  community space of 5% had not included the Granville, Carlton and Rumi's and in fact the loss was 60%.

The workspaces were rigid, enclosed office spaces but the UCL survey showed that people wanted much more creative spaces for activities such as pottery and music.  At a time when people were used to working from home the space offered had to be more than a desk and internet - otherwise people would continue to work from home.

Green spaces were also important. Brent has a very low ratio of green space per person and regeneration will decrease the amount of green space.  And of course densification is going to increase the population significantly. During the pandemic green space became an important outdoor safe space for mental and physical health as well as a place to catch up with neighbours.  It also lent itself to food production and community gardening.

Summarising the recommendations (full details below) Dr Pablo Sendra listed:

1. No loss of community space

2. Creative and well-equipped workspaces

3. Address potential conflict between users (quiet activities versus noisy or messy)

4. Welcoming space to socialise

5. Diverse types of community spaces

6. Spaces for emotional support

7. Activities for young people

8. Flexible and well-equipped green space

9. Local food production and gardening

10. Inclusive process for decision making

11. Involvement of the community in the running of the buildings

12. Work on a resilient funding model.

In discussion questions were asked about the possibility of legal action against Brent Council over its decisions in the light of the research findings. whether the council had carried out a lawful consultation and how the council's action stood regarding the Equality Act.

Asked what next Pablo said that it was now a matter for the community to mobilise itself using the research findings to ensure that they maintained, managed and improved the good space that they had.

After the meeting Leslie Barson said:

Granville Community Kitchen is  very pleased to have this research that identifies and clarifies what needs to be done and why to safeguard The Granville and The Carlton as multi purpose community spaces. We hope the Council will find it useful too and help the South Kilburn community achieve the report's recommendations.

Pete Firmin, a local resident, queried:

When Brent says there has been little loss of green space with regeneration in South Kilburn, I wonder whether they take account of the fact that much of the green space previously was open to all, yet now much of such space is reserved for residents of certain blocks. And green space now is more more patchwork - many smaller spaces, rather than larger ones which allow for ball games etc.

 

The report implies that the Granville/Carlton Centres, whatever else is going on there, are under community control. They never have been and are not now. They are under the control of Council-appointed bodies, with South Kilburn residents having very limited say in their use.


Monday 7 February 2022

Camden and Brent agree redesignation of the Kilburn Neighbourhood Forum

 Following consideration of responses, both Brent and Camden Councils approved the application to re-designate the Kilburn Neighbourhood Forum.

This means the Kilburn Neighbourhood Forum will be able to continue the preparation of a neighbourhood plan in their area. 

South Kilburn is not included in the Forum.

Consultation responses can be found HERE


Wednesday 2 February 2022

Observations on South Kilburn in the light of the Brent Local Plan

 Guest post by David Walton of FLASK

The new proposed Brent Local Plan to year 2041 is set to be put for adoption to Full Council on 24th February 2022.

 

Government Planning Inspectors in January 2022 put forward their final report and modifications to Brent Council. Here are some South Kilburn (soon to be Tall Building Zone (?) local observations…….

 

South Kilburn Growth Area, South East Place (one of 7 large often internally un-related and un-relatable Brent Plan 'places') is excluded from being part of Kilburn Neighbourhood Forum Plan for Kilburn Town (Kilburn electoral ward), but is where Kilburn Town (Kilburn electoral ward) will tower and excluded mega population grow - a bit like Wembley non City, a bizarre, colonial and fractured approach to Brent’s major change.

 

It is of note that these modifications that all site allocation insert plans for South Kilburn have been removed by inspectors from this new Brent Local Plan. I suppose that is one solution to resident questions, but this future engagement is unhelpful as South Kilburn has so many 'site allocations' (knowns and unknowns) pending which must now rely (unlike for other Brent places) entirely on words. Some title headings for new sites have had modifications removed- why not keep a plan saying that current state school land uses or public open space land uses are become new 'site allocation' opportunities instead?

 

It is also worth noting that many South Kilburn large 'sites' don’t even make this modified plan, for example the Cullen House/ station car park ( long land banked), new Peel Square with its 16 storey Countryside tower yet to be built,  Carlton Granville Community and Education Centres, Brent housing plan 'other ideas site' and more….. What are the infrastructure planning requirements for this plan sites denied- none? Should flood alleviation infrastructure and social infrastructure not be stated in Policy BSEGA1 South Kilburn Growth Area? There is certainly a lot less social and health infrastructure required than the 2010 SKGA plan and that was a lot less required than the 2004 Neighbourhood Plan offer (2016 Brent cancelled).

 

The reality is that South Kilburn's population is being increased 6 fold from 6,000 in year 2000 to 36,000 by 2041 (sites hidden/ 'moveable feast' ambiguities added). Modification here is clearly all about the scale of the South Kilburn Mega Growth being kept carefully under the radar of Brent wider social and public health/ recreation strategic infrastructure investment for massive population growth..

 

Of the South Kilburn site allocations which Planning Inspectors modifications:

 

BSESA1 Austin House and public park demolition. South Kilburn Air Management Area (SKAMA) / 'a car free development should be the starting point.' Infrastructure planning requirements- 'Thames Water has indicated that upgrades to the wastewater system are likely to be required.'

 

'Are likely to be required' is the key get out clause here, as Brent despite social rent housing clearing since 2005 has yet to produce a detailed Flood Risk Assessment for any of its many South Kilburn Masterplan(s) for massed help-to buy/ affordable housing on a flood plateau. As regards future floods baked-in by the corporate risk appetite for removal of all existing public owned natural flood defences with new builds no longer being built at raised level either, South Kilburn people will have to ' learn to live with it?' and with the costs involved.

 

What is also interesting is that there are so few site social infrastructure planning requirements for new South Kilburn Growth Area, which is surprising given enormous population growth. This makes the new Brent Local Plan an inequalities/ non citizen zones Brent 'Slum Dog Billionaires' policies document towards 2041 as regards South Kilburn. Very much parallel development and as if Grenfell, Windrush and pandemic simply never happened and the planning reform bill had not been cancelled as being ill advised in 2021 either.

 

The modifications continue…….

 

BSESA2 Blake Court and public park demolition; SKAMA/ a car free development…. Despite being adjacent to Austin House public park flood defence, no infrastructure planning requirements at all?

 

BSESA3 Carlton House and Carlton Hall demolition. SKAMA / a car free development….Despite a community hall and public green space attached being demolished- Infrastructure planning requirements - zero according to Inspectors?

 

BSESA4 Carlton Vale Infant School demolition. SKAKMA/ not car free as next to the Westminster boundary? Inspectors state that vehicle access between Malvern Road and Carlton Vale is 'proposed' to be closed, which is a bizarre planning statement given that vehicles have been closed from Malvern Road to Carlton Vale since the 1960's, this at that time to prevent regular traffic accidents near the schools and central park. Malvern Road is a Brent long established traffic calmed one way street so what is there to propose? Is the intent to open Malvern Road to two way traffic? SKAMA what SKAMA?

 

A land swap with Wordsworth and Maesfield House demolitions is proposed for this school’s new site when it becomes mono-housing. This school is currently central public park side located.

 

BSESA5 Craik Court demolition. SKAMA/ car free development. Public green open space with veteran trees and community hall demolished. Infrastructure planning requirements-non?

 

BSESA6 Crone Court and Zangwill House demolitions. SKAMA/ car free. Public open space loss, yet the only Infrastucture planning requirement – water supply and waste water infrastructure upgrades possibly.

 

BSESA7 Dickens House and public park demolition. SKAMA/car free. Infrastructure planning requirements water supply and waste water upgrades hopefully.

 

BSESA8 Hereford House and Exeter Court, play areas demolitions. SKAMA/ car free. 'Development must be consistent with the recommendations of Brent Local Strategic Flood Risk Assessment Level 2' Infratructure planning requirement. Granville Road Public Open Space (see BSESA11) is to be re-located here at this BSESA8 site. Not very helpful that this requirement Inspectors term 'open space' as that will mean fully private enclosed green space thereby rendered useless to the wider community.

 

BSESA9. The Inspector doesn't dare to even write Kilburn Park Foundation School demolition anymore. The 'site' created by this will be of ambiguous status as for example SKAMA/ car free development is stated. Then Inspectors later say that the demolition site created will be a park, so a new car free park?

 

This school land use being built on re-locates to Wordsworth and Maesfield sites but also onto the South Kilburn Public Open Space, Brent Kilburns only park sized park, demolishing its bio-diverse veteran tree woodland area no less!

 

BSESA10 Neville House, public open space and Winterleys demolition. SKAMA/car free. Infrastructure planning requirements- water supply and waste water upgrades possible.

 

BSESA11 Again, Inspectors dared not name the site which (upgraded and invested in in 2010) is the remains of the once grand scale Granville Road Public Open Space and flood defence. Less 'public open' too this in recent years as Brent Master Developer has been land bank locking it up on and off. SKAMA/car free. Infrastructure planning requirements- waste water upgrades only. So a no public open space replacement is planning required in a flatted  (no gardens) area of public open space deficiency?

 

BSESA12 Wordsworth., Maesfield and part of South Kilburn Public Open Space. SKAMA/ car free. Infrastructure planning requirements- new school(s) to replace the two school sites being demolished for housing. Water supply and drainage upgrades? There is no planning legal requirement stated by Inspectors to replace the large chunk of South Kilburn Public Open Space veteran tree woodland area that both school(s) sold for housing will be re-built on?

 

BSESA13 Again Inspectors unhelpfully decided to abandon naming John Ratcliffe House demolition. SKAMA. Infrastructure planning requirements- waste water upgrades only. 

 

BSESA14 William Dunbar and William Saville House, community hall demolition. SKAMA/ car free housing. Infrastructure planning requirements- water supply and waste upgrades only.

 

BSESA15 Not site named again, the UK Albanian Muslim Community and Cultural Centre. SKAMA/ car free housing. Infrastructure planning requirements- water and waste water supply upgrades only.

 

BSESA16 Oxford Kilburn Club demolition. SKAMA/ car free housing.

Infrastructure planning requirements- Replace club either on or off site (elsewhere)? Water supply and waste water upgrade.

After Brent's take, the OK Club took the lion's share of New Deal for Communities government funds (their first project being to employ a professional fundraiser). It will be interesting to finally see if this by community investment of scarce public funds made any sense now when the OK Club now monumentally 'cashes in?'     

 

 

To add, please look at Article 4 (1) Directions published by Brent in July 2021 which includes an SK Inset Map with at least some of this site allocations red-line box's colonialist horrors illustrated. Horrors (not mapped in the Planning Inspectors modified Brent Local Plan of Jan 2022), with Brent South Kilburn mono-colonial-overdevelopment zones new plan to build on current land uses such as South Public Open Space woodland, Granville Road Public Open Space, Kilburn Park Foundation School, Carlton Vale Infants School and Dickens Austen Public Open Space. This all comes into effect 1st August 2022.

 

The term Growth Area from 2010 BLP should not be retained in this new Brent Local Plan 2022 regarding South Kilburn given the new planning bills 2021 suspension. While underground car parks everywhere as separate 'business' opportunities and the doubling highways by Brent in SK zone should also be made public.

 

Most of the requirements from the 2010 SKGA plan were not landlord actioned and  in the new plan become cancelled requirements. 2022 SKGA South Kilburn plan infrastructure requirements is for flats as literally the only infrastructure and at densities as yet unseen in the UK! Vague Policy BSEGA1 South Kilburn Growth Area is simply not written into later 'site allocations' infrastructure planning requirements or is ambiguously stated, the same for the BSEGA1 new sites not mentioned at all- no infrastructure planning requirements for them no doubt either?

AnonymousA new England-led 'sovereign take back control' South Kilburn for project Global Britain, of high tax take (tax as tribute for simply being allowed to live in the UK third class)- no social, health, shared services towered zones (a social rent estates level and up/ tower, level and up/tower, again and again as of such poor flood area build quality). A zone where no one is or ever can live a full UK citizen's life, rights, health and wellbeing supports and chances- this all by government Global Britain design.

A mega density non place for non citizens is 2041 guaranteed by these Inspectors modifications and residents concerns were not listened to and not respected. This South Kilburn zoned corporate colony for feeding Global Britain Slum Dog Billionaires risk appetite dines on and on- the South Kilburn 'moveable feast'.

 

David Walton

FLASK (Flood Local Action South Kilburn)