Thursday, 16 March 2017

Brent Planners recommend approval of Spurs' bid to increase number of full capacity events at Wembley Stadium

Brent Planning Committee will decide the application to increase the number of full capacity events at Wembley Stadium on Thursday March 23rd. The planners recommend approval 'on balance' and in the face of opposition from local residents and Barry Gardiner MP and Bob Blackman MP. After discussions the number of additional major events proposed has been reduced from 31 to 22. The planning commitee will be held at the earlier time of 6.30pm at Brent Civic Centre.

This is the officers' conclusion:

-->
123.    The objections received indicate that there is a level of impact currently experienced by events at the stadium. Comments received suggest that these mainly fall under the headings of anti-social behaviour and transport. Some impacts are expected, as it is a large stadium in a location with residents and businesses nearby.

124.    Additional events can take place at the stadium irrespective of the outcome of the application. However, those events that are beyond the existing cap would be limited to a capacity of approximately 51,000.

125.    The original cap on events was imposed to manage the impacts until such time as specific transport improvements had been made. Whilst most of these have taken place, not all of them have been realised. Circumstances have changed since the original planning permission in 2002, which suggest that the final piece of transport infrastructure (the Stadium Access Corridor) will not be provided in the originally envisaged form, but will be a variant of this. A further change is the level of development within the area, which has increased the population and will continue to do so. Therefore, the Council considers that the cap remains relevant, and any further impact associated with the additional events must therefore be assessed.

126.    Clearly, to increase the number of events to accommodate Tottenham Hotspur would imply a commensurate increase in the impact, albeit that it is proposed to be temporary for 12 months. In addition, following discussions the number of additional major events has also been decreased from 31 to 22, which would reduced the number of instances within which those impacts are apparent over that 12 month period.

127.    In analysing the impacts there has been some concern about the level of economic

benefit which would result, and this is primarily centred on visitor expenditure. In any event it seems common sense that there would be winners and losers on event days, dependent on the type of business. This makes it all the more important that the social impacts on event days are further mitigated. A number of additional measures have been secured to deal with some of these issues.

128.    Transportation issues have been extensively raised, and there are ongoing efforts to reduce the number of vehicles on a match day. A number of mitigation measures are proposed to continue this work. Some of these allow for existing work to continue, and others are new or updated. The pirate parking initiative is considered particularly important. On an individual event basis, Tottenham Hotspur do have the ability to influence their supporters’ behaviour over the course of a year, which is more difficult than for visitors on a one-off basis such as the FA Cup final. Addressing transport issues will also contribute to reducing noise and air quality issues.

129.    In summary, it is recognised that there is a level of impact being caused by major events now, and that this would increase with an increase in the number of high capacity major events. However, the measures proposed would ensure that this is mollified as much as is reasonably achievable. All are considered necessary to mitigate the increased number of matches which this application proposes. A further consideration is that Tottenham Hotspur could use the stadium for major events up to 51,000 now without restriction, and were they to do that then no additional mitigation measures would be formally secured. The proposed additional mitigation would apply to Tottenham Hotspur events, and with some of these being within the existing cap would represent a theoretical improvement for these major events.

130.    The proposal is, on balance, recommended for approval. 

Full Report HERE


Latest on the Grunwick 40 commemorative mural


Foer those wondering what had happened with the Grunwich 40th anniversary mural here is a message from Anna Ferrie, the mural artist and the Grunwick 40 team.

The exhibition is in its last weeks  at Willesden Library finishing at 5pm on Sunday March 26th.

We wanted to let you know about progress with the Grunwick 40 commemorative mural as many of you have been asking for an update. We had hoped to have the mural up by now but issues with site permissions and bureaucracy have meant that we can't yet move forward to install the panels. 

However, the mural composite designs are done and incorporate all of the artwork that was produced in the workshops. We are working hard to speed up the process to ensure the mural can be installed and unveiled within the next few months and we hope be able to bring you a firm date soon. In the meantime, you may be interested in The Art of Protest event later this month where we'll be discussing the different ways that art can be used to remember radical histories. We hope to see you either there or when we launch the mural!

Anna Ferrie and the Grunwick 40 team


https://www.eventbrite.co.uk/e/the-art-of-protest-tickets-32435324930

Wednesday, 15 March 2017

Barry Gardiner MP to meet with residents on Wembley Stadium controversy - Saturday




Barry Gardiner MP (Brent North) has arranged to meeting with residents concerned about the potential impact of the proposal to increase the number of full capacity events at Wembley Stadium. The application goes to Planning Committee on Thursday March 23rd.


The meeting will take place at St Cuthbert's Church 214 Carlton Ave West Wembley HA0 3QY on Saturday at 10.30am.

Capacity is limited (unlike the Stadium) to the first 30 residents or representatives to respond by emailing this blog with name/s at martinrfrancis@virginmedia.com (I will pass on to the organiser) or commenting on the NextDoor website LINK 



182 bus stops nearby

Inadequacy of Spur's Wembley Stadium Environmental Statement exposed

With the Evening Standard anticipating Brent planners statement on the Wembey Stadium application for additional full capacity soon, ahead of the March 23rd Planning Committee. I thought it worth publishing this submission from a resident of Corringham Road, addressing the applicant's Environmental Statement. LINK

In addition I publish the supporting submission from Haringey Council at the end of this article.

Comments on the Environmental Statement (January 2017) to the Temporary Variation to the Event Cap at Wembley Stadium - Document Chapter C - Socio-Economics

There are a number of points to make with reference to the Environmental Statement (ES) accompanying the Planning Reference 17/0368 - the application by Wembley National Stadium Limited (WNSL) - and in particular to the Socio-Economic aspects.

The most important points are as follows:

1. It has almost no economic or quantitative analysis at all, as opposed to just assumptions, and its conclusions cannot be supported in the absence of further work and also a properly produced cost-benefit analysis.

2. It does not deal with any likely costs, and has only skimmed over the so called "beneficial socio-economic" impacts. The coverage and the quality of the analysis are far from adequate.

3. The conclusions under the heading "Potential Effects" are not robust, and there has to be much further and more careful work done to look at the likely negative impacts on the local economy.

4. What about the economic costs of congestion, stress and strain on the local services and population, the crowding out of other economic activity, the inconvenience caused by hugely larger attendances at more much larger scale events at the Stadium?

5. There is inadequate analysis of the location of possible additional expenditures, either within or outside the stadium?

How much extra and additional economic benefit accrues to the local area and population as opposed to just within the stadium? This is certainly not clear from the application documents, and is vitally important in coming to any decisions.

6. The figures in the conclusion in the summary of socio-economic benefits that expenditures of £43.5m and £14.5m (excluding traffic) can be expected locally are based not on calculations done at the Wembley site but are based on a primary survey by THFC of spectators to White Hart Lane.

It is stated in the application documents in paragraph C5.14 of the ES that "if this expenditure profile ..... were to be transferred to Wembley Stadium during the 2017-18 season, this could support (my bold) £43.5 million of expenditure.......this would mean £14.5 million of expenditure would be available for spending on food, drink and other ancillary items at Wembley".

However, these figures are purely assumptions. There is no robust analysis or justification that these are likely to be appropriate, and are certainly not accompanied by any corresponding costs which should have been taken into account.

7. Paragraph C5.16 of the ES states that "On this basis, taking into account employment and visitor expenditure effects, it is assessed that the impact of the temporary variation of the event cap will result in a moderate positive impact on the local economy for the duration of the 2017-18 football season" (my bold).

How can any conclusion follow from the implausible assumptions in paragraph C5.14 stated above?

8. In the document entitled "Temporary Variation to Event Cap at Wembley Stadium..." written by Nathaniel Lichfield & Partners, it is clear from paragraph 6.5 that the conclusions of the environmental impact assessment should have covered all four aspects namely (1) Socio-economic (2) Transportation (3)Air Quality and (4) Noise and Vibration.

However, in the summary to this document, in paragraph 9.7, it is stated that "this Statement demonstrates that the proposals accord within planning policy and will not result in any unacceptable effects in terms of transport, noise and vibration and air quality impacts".

But, where is the reassurance about socio-economic impacts? It is strange that it should be omitted if there was a clear conclusion that this was also acceptable.

9. There is no clear analysis of which geographical area the claimed benefits are supposed to support. The definition of the area around the Stadium is important to identify, especially if the costs as well as benefits are to be assessed. The costs are likely to be spread around the wider neighbourhood via aspects such as traffic congestion, parking problems, noise and safety. Why have these not been included? It is common practice to include some valuation for these impacts in a properly worked cost-benefit analysis.

10. There is very little understanding of the scale factors associated with increasing the numbers of visitors to the Stadium from a maximum of 51,000 to 90,000 on an extra 31 days a year. A proper analysis would have shown a much better awareness of the huge impacts such large crowds will have. The various comments in the papers accompanying the planning application imply that all impacts will be minor.

11. As an example of the lack of understanding of the likely impacts of scale is paragraph G6.4 in the Summary and Conclusions of the Environmental Statement, which states that: "Minor negative residual effects remain in relation to specific sensitive recepto Comments on the Environmental Statement (January 2017) to the Temporary Variation to the Event Cap at Wembley Stadium ? Document Chapter C ? Socio-Economics

There are a number of points to make with reference to the Environmental Statement (ES) accompanying the Planning Reference 17/0368 - the application by Wembley National Stadium Limited (WNSL) - and in particular to the Socio-Economic aspects.

The most important points are as follows:

It has almost no economic or quantitative analysis at all, as opposed to just assumptions, and its conclusions cannot be supported in the absence of further work and also a properly produced cost-benefit analysis.

It does not deal with any likely costs, and has only skimmed over the so called 'beneficial socio-economic' impacts.  The coverage and the quality of the analysis are far from adequate.

The conclusions under the heading 'Potential Effects' are not robust, and there has to be much further and more careful work done to look at the likely negative impacts on the local economy.

What about the economic costs of congestion, stress and strain on the local services and population, the crowding out of other economic activity, the inconvenience caused by hugely larger attendances at more much larger scale events at the Stadium?

There is inadequate analysis of the location of possible additional expenditures, either within or outside the stadium?

How much extra and additional economic benefit accrues to the local area and population as opposed to just within the stadium? This is certainly not clear from the application documents, and is vitally important in coming to any decisions.

The figures in the conclusion in the summary of socio-economic benefits that expenditures of £43.5m and £14.5m (excluding traffic) can be expected locally are based not on calculations done at the Wembley site but are based on a primary survey by THFC of spectators to White Hart Lane.

It is stated in the application documents in paragraph C5.14 of the ES that 'if this expenditure profile ..... were to be transferred to Wembley Stadium during the 2017-18 season, this could support (my bold) £43.5 million of expenditure.......this would mean £14.5 million of expenditure would be available for spending on food, drink and other ancillary items at Wembley'. 

However, these figures are purely assumptions. There is no robust analysis or justification that these are likely to be appropriate, and are certainly not accompanied by any corresponding costs which should have been taken into account.

Paragraph C5.16 of the ES states that 'On this basis, taking into account employment and visitor expenditure effects, it is assessed that the impact of the temporary variation of the event cap will result in a moderate positive impact on the local economy for the duration of the 2017-18 football season' (my bold).
How can any conclusion follow from the implausible assumptions in paragraph C5.14 stated above?

In the document entitled 'Temporary Variation to Event Cap at Wembley Stadium...' written by Nathaniel Lichfield & Partners, it is clear from paragraph 6.5 that the conclusions of the environmental impact assessment should have covered all four aspects namely (1) Socio-economic (2) Transportation (3)Air Quality and (4) Noise and Vibration.
However, in the summary to this document, in paragraph 9.7, it is stated that 'this Statement demonstrates that the proposals accord within planning policy and will not result in any unacceptable effects in terms of transport, noise and vibration and air quality impacts'.
But, where is the reassurance about socio-economic impacts? It is strange that it should be omitted if there was a clear conclusion that this was also acceptable.

There is no clear analysis of which geographical area the claimed benefits are supposed to support. The definition of the area around the Stadium is important to identify, especially if the costs as well as benefits are to be assessed. The costs are likely to be spread around the wider neighbourhood via aspects such as traffic congestion, parking problems, noise and safety. Why have these not been included? It is common practice to include some valuation for these impacts in a properly worked cost-benefit analysis.

There is very little understanding of the scale factors associated with increasing the numbers of visitors to the Stadium from a maximum of 51,000 to 90,000 on an extra 31 days a year. A proper analysis would have shown a much better awareness of the huge impacts such large crowds will have. The various comments in the papers accompanying the planning application imply that all impacts will be minor.

As an example of the lack of understanding of the likely impacts of scale is paragraph G6.4 in the Summary and Conclusions of the Environmental Statement, which states that: 'Minor negative residual effects remain in relation to specific sensitive receptors in relation to bus services impacted by additional vehicular traffic in the immediate periods prior and post matches. The additional mitigation measures proposed to encourage public transport will assist in minimising this effect as far as possible. These adverse impacts should be balanced against the beneficial socio-economic effects arising from the proposal.'

Well, this is not good enough. What does 'as far as possible' mean? Why have these, as well as lots of other negative impacts, not been costed?

Furthermore, why has there been the assumption that they 'should be balanced' against some inadequately analysed socio-economic benefits? Where are the figures to accompany this sort of comment in the Conclusions?

As an indication of how little account has been taken of the scale factors associated with the proposed changes, and the overall lack of coverage of issues that cause detriment or negative impacts, the Environmental Statement contains in its Summary & Conclusion the following key points:

Paragraph C8.5: in relation to local air quality 'No mitigation measures are required'.

Paragraph C8.6: comments 'In terms of noise and vibration, it is considered that crowd noise from the additional sporting events would have a negligible impact.....

There are no further mitigation measures that are required other than those considered or already implemented'. (My bold)

Paragraph C8.7: comments in conclusion from the ES that 'The proposed variation to the event cap to allow THFC to use Wembley Stadium for the 2017-18 will bring significant additional expenditure and employment to Wembley and its surrounding area'. (my bold)

Finally, in my view the analysis done for this Environmental Statement, which is a crucial input into any decision as to whether to allow the Planning Application 17/0368 to get approval, is not sufficiently robust to form the basis for any decision.

There are sufficient problems, gaps and inconsistencies in its coverage to require a further and better piece of work to be undertaken and provided in writing to the Brent Council Planning Department before any decision is taken.

The impact on the geographical area close to the Stadium of the proposed changes embodied in the Planning Application is so considerable that this information must be supplied.

Meanwhile Haringey Council has submitted its support for full capacity matches to be played at Wembley.

Leisure Services, Haringey Council, Alexandra House, 10 Station Road, Wood Green, London, N22 7TR 

Haringey Council Parks & Leisure Services support the application for Tottenham Hotspur to play all of its games at Wembley at full capacity.

We have seen considerable benefits for our community from Tottenham Hotspur's work in our Borough with their Foundation having spent time for example working with employers in the area, the Job Centre as well as in schools across the area.

Through an increase in the number of people attending and the size of the events, we believe there will be increased opportunities for local business, greater employment benefits on events days and a general bump to the local economy.

Additionally, having engaged with the Tottenham Hotspur Foundation, we are pleased that this application outlines a further commitment to enhancing their programme of activity in the borough of Brent and expanding it during their year in the borough. Through this work, we believe there will be some real opportunities to develop employment and skills opportunities beyond just event days and not just in industries you would associate with Wembley Stadium or football. We look forward to working with them to develop these programmes.

With regard to the event's themselves, while event days do come with issues for the community, we believe from our own experience that the additional mitigation measures put in place to manage them at 90,000 will make them considerably better run events than we currently have at the stadium. We welcome the extra efforts being made by the Club and Wembley to address the issues which arise regardless of the stadium capacity and hope that by accepting this application we will see the benefit of those measures positively impacting the area on event days.


Strike at Ark Elvin Academy, Wembley, tomorrow



PICKET LINE - Thursday 16 March at Ark Elvin Academy, Cecil Avenue,Wembley, HA9 7DU.
7am onwards.

NUT, ATL and NAS/UWT members at Ark Elvin Academy will stage their  first day of strike action tomorrow against ten proposed redundancies -part of the fightback against government education cuts.

All those who are sympathetic to the strike are welcome to join the picket line.

Ark Elvin was formerly Copland High School and was forced to become an academy despite opposition from staff, parents and students.

Monday, 13 March 2017

Appeal to help save the Corrib


Outside the Corrib, 76-78 Salusbury Road, Queens Parkm NW6 6PA

From Friends of the Corrib

Now the Planning application is published, it’s a clear plan to KILL the CORRIB.

We urge you ALL to do one more thing to help Save the Corrib.

Please object to Brent Council Planning

EACH objection increases the chances of keeping the Corrib Community Rooms and Pub forever.

Tell the planners what the community rooms and pub mean to you and what you used it for especially the Function Rooms which had all the dance classes, pensioner meetings and other events and/or just give your views as why it should not be turned into luxury flats - as we should not lose community spaces.

You can just object to the principal of the destruction of community space, especially this one, protected by a 106 agreement protecting money originally spent by Brent when it started for the community. The more you tell them the more weight it will have.

How to object.

You can email the planning officer directly at:
barry.henn@brent.gov.uk

To be accepted by planning you do need to include your name and address in the email.
It does not matter if you are not local – you just need to feel it’s important

Please copy in savethecorrib2017@gmail.com so we can ensure that Brent note all the letters received.

OR (the most sure way)

Go on the Brent Website, register and then object on line.
Paste below into your search engine to register.

https://myaccount.brent.gov.uk/Web/PublicPages/IR1_Register.aspx_ga=1.122443147.1434451185.1368051210

Then paste in the site below

https://pa.brent.gov.uk/online-applications/applicationDetails.do?activeTab=documents&keyVal=DCAPR_131699

Click on Make a Comment and add your concerns

Tell them things you could do and events that this place had and the value of the function rooms both in the past and into a promising future

Summary of the Developers plan.

To turn the community rooms on the first floor, into 6 luxury flats and make a £4M profit.
As a sop they have offered a function room in the pub, which will allow some community use for 3 evenings a week, making for a much reduced and commercially dead pub. Of course if the pub fails, more flats.

This planning application means the loss of 530m2 of community space, space that was originally brought with public money and is now protected by both an ACV order and by a Section 106 covenant. The 106 is a council owned legal restriction that prevents the owner building flats on the first floor. We urge Brent NOT to break this 106 covenant but to honour and cherish it.

To read the planning application in full, go to:

https://pa.brent.gov.uk/online-applications/applicationDetails.do?activeTab=documents&keyVal=DCAPR_131699

The documents should read are:
1) 170116 - planning statement v756767850000.pdf
2) Statement of community involvement56767850001.pdf

NB: The Sir Richard Steele in Chalk Farm is a similar pub with function room and Camden and the Planning Inspector both turned down this conversion to flats so we say that Brent should do the same here.

http://archive.camdennewjournal.com/steeleappeal

Also ask friends etc. to sign the petition, we are aiming at 2000 signatures.

http://you.38degrees.org.uk/petitions/save-the-corrib-pubs-community-rooms

Thank you for standing with us on this issue. 

Duffy forces Council U-turn on out-sourcing

Following recent controversy about the Kingdom littering contract, including the Scrutiny Committee discussion from which the public were excluded and the revelation that no formal minutes existed for the original contract meeting between officers and Kingdom LINK, it appears that Cllr John Duffy may have achieved a break-through, forcing a re-think by the lead member and Cabinet.

I understand that following Duffy's production of figures showing that an in-house solution would offer better value for money than the Kingdom contract, that this is now likely to happen.

Duffy has maintained that the original Cabinet decision to out-source the contract wasted over £100,000 of the environmental budget at a time when council finance was under pressure from government cuts.  Duffy challenged the Cabinet's claim that Kingdom paid the London Living Wage and it does now appear that the company was not LLW accredited and that rates are far below those for similar officers directly employed in the public sector.

In an interchange earlier in the Scrutiny meeting Duffy quoted 73 fly-tipping fines versus 4,000 fixed penalty, notices mainly for dropping fag ends. Cllr Southwood said the proportion of FPNs for fag ends had been reduced to nearer 60% after talks with Kingdom. Cllr Duffy claimed that this was still still out of balance. An Environment Department officer claimed it was more difficult than people might think to get admissable evidence on the perpetrator of  fly-tipping. Even if addressed letters were found inside black bags you still had to prove the addressee was responsible for the fly-tipping.

The figures suggest that Duffy has been vindicated and that an in-house service will not only produce a better service and value for money for council tax payers but that workers involved will secure  better pay and conditions.



Saturday, 11 March 2017

Tomorrow's road closures in Wembley and Kingsbury for Half Marathon


The Vitality North London Half Marathon takes place on Sunday 12th March passing through Brent  and Barnet with about 10,000 runners expected.

This will mean road closures from early morning on the Sunday:

Olympic Way (from 4.45am)
Wembley Park Boulevard (4.45am)
Royal Route (4.45am)
Perimeter Way (4.45am)
Engineers Way (6.45am)
Fulton Road (6.45am)
Brook Avenue (4.45am - between Olympic Sq access gate and Bridge Road)
Bridge Road (4.45am between Brook Avenue and Forty Lane)
Forty Lane  (7am)
The Paddocks (7am)
Fryent Way (7am)
Valley Drive (7am)
Kingsbury Road (7am between Valley Drive and Roe Green)
Roe Green (7am)
Hay Lane (7am)
Edgware Road (8.545am between Hay Lane and Colindale Avenue)
Slough Lane (7am between Kingsbury Road and Salmon Street)
Salmon Street (7am between Slough Lane and the Paddocks)

The race will start at 8am and a 'dynamic reopening schedule' will operate to ensure roads are open as soon as possible once runners have completed each section of the route and when it is safe and feasible to do so. Roads will begin to re-open from 10.15am and most will be re-opened by 12.45pm. Brook Avenue and Bridge Road will be the final roads to re-open at 1.45pm.

WEBSITE