Guest post by Philip Grant in a personal capacity
In January 2020, Brent’s Cabinet approved proposals for a new adult
education college, and 65 affordable homes, on the site of the existing Brent
Start building at 1 Morland Gardens in Stonebridge. They delegated authority
to make all the Key Decisions for this project to the then Strategic Director for
Regeneration (in consultation with a Lead Member). His report told them that
work on the new building should be completed by the summer of 2022:-
Morland Gardens “Delivery Timetable” from the report to Cabinet, January
2020.
In fact, the scheme had already been informally approved by the Leader,
and then Deputy Leader and Lead Members for Education and Housing, at a meeting
with the project team in February 2019. Then they were told that 89 new homes
could be built on the site. That number was later reduced to 65, as even
Brent’s planners would not agree that the impact on neighbouring residents
(loss of light, etc.) of the 89-home design would be ‘acceptable’.
The proposal had started off in 2018 as an updated college and some
new housing. The original design by the architects would have retained the
locally-listed Victorian villa, and developed the site in phases, so that there
was no need for Brent Start to by decanted. There was a viable alternative to the scheme which the Cabinet approved. However, it seems that the Council were
determined to build as many new homes as they could on the college site, even
though it meant demolishing a valuable heritage asset their own policies
promised to protect, and that was the first of many mistakes they have made on this project.
Architect’s image of the proposed new building (viewed from across
Brentfield Road).
In August 2020, the Council controversially obtained planning
consent for the development, despite
strong local opposition. It was soon celebrating its “award winning” Morland Gardens scheme, and the 65 new homes it would deliver. Two years later, there are new
residents at 1 Morland Gardens, but in the original building, not the new one
pictured above.
The Brent Start college was moved out earlier this year to a “temporary
home” in the former Stonebridge School Annexe. (The adaptations to the annexe
cost at least £1.2m, and the building will be demolished once the college
leaves, as it is on the site of Brent’s Twybridge Way 67-home housing scheme, which was given planning consent in May 2020, and should be nearing
completion now!) That left 1 Morland Gardens vacant.
What do you do with a large empty building, when the catalogue of
mistakes you’ve made means that you are still not ready to go ahead with its
redevelopment? In May 2022, Brent contacted Live-in Guardians, and by early July this organisation was housing mainly young single
people in the former college building.
An Instagram advert for Live-in Guardians at 1 Morland Gardens, July
2022.
I was first aware of Live-in Guardians (“LIG”) there when I attended a
site meeting with Brent’s Project Manager on 26 July, to discuss my objections to the proposed Stopping-up Order for the highway outside the property. There was a sign on the gateway
to say that they were providing live-in protection for the building, and a
resident would not let us enter because the Officer had not arranged access in
advance.
I’m interested in all aspects of the Morland Gardens project, so I put
in an FoI request for a copy of the Council’s agreement with LIG. This has been
supplied to me, and as live-in guardianship is an idea which may be of wider
interest, to single people (or couples) in need of an affordable short-term
home as well as to property owners, I will include some information and
extracts from it below.
The opening paragraphs from Brent’s agreement with LIG.
These “new homes” would not be for people on Brent’s housing waiting
list, so who were they for? The agreement says that up to 26 “Guardians” would
be provided with accommodation at 1 Morland Gardens, and gives details of the
type of person and how LIG selects them.
It sounds from this extract that the Guardians living here will be
people who do need relatively inexpensive accommodation, at a stage where they
are not in a position to rent or buy somewhere more permanent. But how long can
they stay in the building?
The paperwork makes it clear that the Guardians only have a licence to
occupy the premises, subject to the right to 4 weeks’ notice to leave after the
26-week contract period. Their legal status is explained to them on the LIG
website.
From the LIG website.
1 Morland Gardens has been used as a college since 1994, when it was
sympathetically designed around the restored Victorian villa. Turning it into
living accommodation would require some alterations, but as part of the
agreement LIG paid the initial fit-out costs, for things such as installing a
kitchen, 4 extra showers, and carrying out all of the necessary safety checks.
The cost of this work was estimated at up to £17k.
It appears that Brent is getting a good deal out of allowing Guardians
to live at 1 Morland Gardens. The Council would not have to pay a security
company to look after the vacant property. The only expenses they would incur
during the contract period would be the Council Tax or Business Rates, and any
repairs or maintenance which the agreement made them responsible for. And, at
any time after the 26 weeks, they could get vacant possession of the building
and land within its garden walls by giving only four weeks’ notice.
I have to say that I approve of Brent’s decision to allow 1 Morland
Gardens to be used for providing temporary accommodation, rather than remaining
empty after they had moved the Brent Start college out of the building. The
presence of Live-in Guardians will hopefully prevent the beautiful heritage
building from being vandalised (and among the potential vandals, I include Brent Council and the contractors it has
recently hired, perhaps unlawfully, to
demolish it!)
1 Morland Gardens, the former Brent Start college, June 2022.
Another reason why I like Brent’s agreement with LIG (although, on
refection the Council may regret it) is that the 26-week period will last until
at least the end of December 2022. At a Scrutiny Committee meeting on 9 June, Brent’s Strategic Director for Regeneration justified the urgent award
of a c.£38m contract for the Morland Gardens development on the grounds that if
work did not begin on site by August ‘the Council stood to lose the £6.5m GLA
grant towards affordable housing.’
The site is in two parts. They can’t build on the land outside, because
there are open appeals against the proposed Stopping-up Order. Now they can’t
begin any work inside the boundary, because that is legally occupied by Live-in
Guardians. Brent can’t “start on site”, within the terms of their GLA grant
agreement, this month (or this year), because they have no site to start on!
Philip Grant.