Wednesday 22 March 2017

Planning Officers maintain their support for Stadium Planning Application in Supplementary Report

A supplementary report has been published on the eve of Thursday's Planning Committee. LINK It contains more information on mitigation. The Officers maintain their support for the planning application.


Following completion of the committee report, a further 24 letters of representation have been received. Where additional issues have been raised they are noted below, otherwise they are considered to have been dealt with in the main report.

One letter of support

The issues raised are considered to have been addressed within the main report.

23 letters of objection

Objection from one representation citing insufficient notice of the committee, and a request for an additional 3 weeks instead. Also, confusion over when the committee is due to take place. Concern that the additional number of events would result in the roads deteriorating.
The notice period given is considered reasonable and in accordance with the Council’s procedures. There was an error on the earlier communication which stated that the Committee would begin at 7pm and this was corrected last week. The proposal would result in additional journeys, but the mitigation in place is intended to reduce the number of cars as far as possible.
Request for clarification on the need for a section 106 legal agreement, and whether parking permits within the event day management zone would remain free.

A section 106 legal agreement is absolutely necessary to the acceptability of the proposal.

The current charge for a parking permit is £10. The proposal would not change this.

Concern about the noise from helicopters, which would be increased with a greater number of events.

Helicopters can be associated with large events as part of the police operation. The height at which they fly or hover will inevitably vary, and hence so will the noise they generate. However, this is considered to be infrequent and for short periods of time. It is not considered that this alone would increase the level of noise to the point that it is considered unacceptable.
Other issues raised are considered to have been addressed within the main report.

Mitigation

The committee report identified a number of mitigation measures which would be secured within the section 106 legal agreement. Further detail is provided on a number of the additional measures which are proposed over and above those secured through the original agreement dated 23 August 2002. A number of them were detailed within the main report and so are not detailed further. These additional measures to cover individual events are proposed to apply only to the 22 additional major events. They are not proposed to apply to 37 high capacity (51,000-90,000 capacity ) events that can take place under the existing condition.
Event by event mitigation measures, for the additional 22 events proposed
Regulation of Public Safety – The Council’s reasonable costs would be met as part of the application on an event-by-event basis, which would be on a similar basis to what is currently done for street cleaning and the regulation of traffic management. This involves a requirement to attend pre-match meetings and monitoring safety documentation for each event. Inspections would take place (in addition to those which take place during existing major events) to monitor the measures and seek to refine the process.
Alcohol licensing inspections – This would also be related to the Council’s reasonable costs, similar to the regulation of public safety. This involves inspecting licensed premises prior to an event and follow up visits afterwards if there have been complaints.
Illegal street trader – This was highlighted in the list within the main committee report. This is proposed to be removed from the Section 106 legal agreement, but only because there has already been a mechanism established for the previous 4 Tottenham Hotspur events that have taken place at Wembley, which is proposed to continue.
Anti ticket tout initiative – This would also be related to the Council’s reasonable costs, similar to the regulation of public safety. Ticket touts are a feature of many sporting events, and can lead to people being denied the opportunity to view sporting events at a reasonable cost. Touts can obstruct public areas and introduce an element of intimidation. One-off contribution mitigation measures:
Pirate parking initiative – More than £47,000 has been secured to ensure that the existing scheme can continue. The intention is to ensure that parking on land which does not have planning permission for that purpose is addressed, so reducing the number of persons using cars and increasing the number of persons using public transport.
Additional CCTV camera – This was detailed in the main report. The cost for this would be £22,779. In addition, further measures are proposed to those detailed within the main committee report.
Litter bins – In response to a number of objections there would be a contribution of £20,000 for litter bins in and around the stadium and Wembley Town Centre.
Radio system and protective clothing – This would ensure that the current equipment (which is leading to some problems with communication) is replaced by more advanced equipment. This would improve the event day operations, by improving communication when setting up road closures and managing traffic. Ultimately, this would assist in the safe and efficient arrival and departure from events at the stadium. This would be £50,000.
Event day signage – Following an audit of the existing signage a contribution of £60,000 is proposed to improvements, to be secured before the 2017/18 season. This would include a more detailed audit to identify broken signage and identify where more signage is required. There would be maintenance of existing Variable-Message Signs (VMS) and event day flap signs. Additional signage would be provided in areas with insufficient signage. Reference has been had to the tests of whether a section 106 obligation is considered justifiable. As required by Regulation 122 of the Community Infrastructure Regulations 2010 (as amended) a planning obligation may only constitute a reason for granting planning permission if it is: (a) necessary to make the development acceptable in planning terms; (b) directly related to the development; and
(c) fairly and reasonably related in scale and kind to the development. The obligations above, and those which are listed and detailed in the main report, are considered to pass these tests. They are proposed to maintain the existing levels of mitigation for the existing major events (as secured in the original section 106 legal agreement), and to go further for the additional major events proposed by this application.

Update on Tottenham Hotspur

Since the committee report was finalised there have been additional games played. As of 22 March 2017 there are 10 games remaining for Tottenham Hotspur in the Premier League. They remain well placed to be in European competition next year (specifically the group stage of the Champions League). They remain in the FA Cup, which has reached the semi-final stage. This is not considered to change the assumptions on the numbers of games they are likely to play next season.

Conclusion

The additional comments received raise some additional points, which are not considered to change the recommendation. Many of the issues have been raised previously, and are considered to have been addressed in the main report.
This supplementary report provides additional detail on some of the mitigation measures proposed, and some additional measures which go beyond what is contained within the main committee report. They are welcomed and would assist to mitigate the impacts of the greater number of major events which this application proposes.
Recommendation: Remains approval as set out within the committee report